Figure 48
1.
Coupler pin
10. Adjust the floor jack as required to install the bolts
(3/4 inch) on each side (Figure 49). Torque the bolts
to 265 ft-lb (359 N
⋅
m).
Figure 49
1.
3/4 inch bolts
2.
Coupler pin
Note:
The rear tires will need to be removed to
torque the rear bolts (3/4 inch). After torquing the
frame bolts, install the rear tires and torque lug nuts
to 65 to 85 ft-lb (88 to 115 N
⋅
m).
11. Connect the hydraulic pressure hose to the valve
hard line and tank hose to the valve (Figure 50).
Retain the hose plugs for the summer change over.
Note:
Make sure the hoses are not kinked or are
not rubbing against any sharp edges or moving parts.
Note:
Adjust the angle of the fittings to
accommodate the routing of the hoses.
G009488
1
2
Figure 50
1.
Pressure hose
2.
Tank hose
12. Raise the rear of the machine until 2 jack stands can
be positioned under the rear tube at a height that
supports the rear tires 1 to 3 inches (2.5 to 7.5 cm)
off of the ground.
13. Lower the floor jack so the rear frame rests on the
jack stands. Position the floor jack under the center
of the front lift arm pivot tube.
14. Remove the two screws securing each side access
cover and remove the covers (Figure 51).
Figure 51
1.
Access covers
15. Remove the flat washer (1/2 inch) and nut (1/2 inch)
installed on the stud on each bogie pivot (Figure 52).
21