Choose a location and Install the Ground Socket
-
Choose a suitable location.
-
Dig a hole in the centre of the space 600mm deep and 250mm in diameter.
-
Fill the bottom of the hole with 200mm of dry gravel.
-
Fit the ground socket to the end of the main post. Rotate the post in the
ground socket until it locks.
-
Position the Ground Socket and Main Post in the centre of the hole.
-
Support the Main Post and fill the hole with concrete. Use a spirit level to
make sure the Main Post is vertical.
-
Leave the Main Post in the Ground Socket while the concrete sets.
DO NOT USE OR MOVE THE CLOTHESLINE UNTIL THE CONCRETE HAS SET
–
ALLOW AT LEAST 24 HOURS