10
12)
Make sure the pin on the bottom of the cylinder is seated into the hole in the center
of the base plate. Pull the pre-attached leaf chain in both sides up and over the chain
pulley on top of the cylinders. Refer to Fig 9 for HD2P-9000AF Floor Plate Type and Fig.
10 for HD2P-9000AC overhead type.
13) Connecting the hydraulic hoses, as shown on Fig 9 for HD2P-9000AF Floor Plate Type
and Fig 10 for HD2P-9000AC Clear Floor Type.
14) Mount the power unit on lift as shown in Fig. 9 & Fig 10.
15) For the HD2P-9000AF model, mount the floor plate (13.1) as shown in Fig 14.
16) Install the swing arms on the carriages using the included 1 1/2” diameter pins. Check
for proper engagement of the arm lock- the rack on the lock should fully engage the
gear on the arm. Grease these pins to prevent excessive wear.
17) Adjust the carriage cables tension. Adjust each cable to approximately 1/2” side-
to-side play. Check the latch releases to insure the carriage is still sitting on the
appropriate latch.
18) Remove the fill cap from the power unit and fill the oil tank reservoir. To fill the oiltank
resevoir, the lift must be completely lowered. FIll the oil tank with a premium quality
ISO-32, AW-32 or AW-46 Hydraulic Oil.
19) Make the Electrical hookup to the power unit.(220V Single Phase). It is recommended
that a 220 Volt, 30 Amp twist lock plug be installed in the power line just ahead of the
power unit. Size wire for 30-amp circuit.
WARNING:
The wiring must comply with local code. Have a certified licensed
electrician make the electrical hook-up to the power unit. Protect each circuit with time
delay fuse or circuit breaker 208v.230v single Phase. 60Hz 30 Amp.
Summary of Contents for HD2P-9000AC
Page 35: ...32 FIG 12 9000AC 12 PARTS FIG 12 16...
Page 36: ...33 FIG 13 9000AC...
Page 39: ...36 FIG 14 9000AF...
Page 40: ...37 FIG 15 9000AF...
Page 46: ......
Page 47: ...NOTES...