Titan Attachments 191503 Owner'S Manual Download Page 5

 

OPERATION INSTRUCTION  

PRE-OPERATION CHECKLIST 

1.

 

Check for any loose or missing guards and shields on the trencher.  

2.

 

Inspect hoses and hose connections for any leaks. Replace hoses and hose connections as 
necessary.  

3.

 

Check the chain tension before operating the trencher.  

4.

 

Lubricate the trencher’s grease points. Please refer to the “Maintenance Instructions” section 
for this information. 

5.

 

Check for any loose fasteners. Tighten the fasteners as necessary.  

6.

 

Refer to operating machine user’s manual for pre-start instructions.  

7.

 

Review and understand this manual and operating machine manual.  

ATTACHING AND DETACHING TRENCHER 

1.

 

Follow all safety instructions before attaching the trencher.  

2.

 

Attach the trencher to the skid steer mount plate. Verify all pins are secured in the correct 
position.  

3.

 

Connect the hydraulic hoses. Verify that the hoses are clear of any moving parts.  

4.

 

Case Drain line required to operate this implement 

 

OPERATION PROCEDURES 

 

Test the functions of the trencher in a clear, open area with skid steer in idle. Understand the 
controls of the trencher and operating machine before beginning operation.  

 

ALWAYS survey the area prior to working and consider the ground conditions. Avoid 
underground hazards such as utility lines, hidden stumps, etc. 

 

Starting the Trencher 

1.

 

Set trencher parallel to ground, but not yet making contact. 

2.

 

Start the trencher by increasing engine speed in the operating machine. Ensure the chain is 
moving in the correct direction. Slowly increase the trencher’s chain speed.  

3.

 

Increase the trencher’s chain speed until full speed. 

Summary of Contents for 191503

Page 1: ...OWNER S MANUAL MPN s 48TRENCHER SKU s 191503 UPC s 840009205682...

Page 2: ...e engine is still running Always inspect trencher and host machine before operation OPERATIONAL DANGER HAZARDS ALWAYS ensure bystanders are at least 25 FT away from trencher during use Contact with mo...

Page 3: ...3 TRENCHER KEY COMPONENTS 1 Crumber Arm 2 Chain 3 Teeth 4 Chain Tensioning Assembly 5 Hydraulic Motor 6 Hydraulic Hoses 7 Manual Side Shift Adjustment Pin 8 Mount Plate 9 Auger 10 Skid Plate...

Page 4: ...4 TRENCHER SPECIFICATIONS...

Page 5: ...her 2 Attach the trencher to the skid steer mount plate Verify all pins are secured in the correct position 3 Connect the hydraulic hoses Verify that the hoses are clear of any moving parts 4 Case Dra...

Page 6: ...ct with the ground slowly reverse the skid steer machine Avoid stalling the chain STOPPING THE TRENCHER 1 Set engine speed to low idle and raise the trencher above ground level 2 Stop operating machin...

Page 7: ...for varying trenching conditions this implement comes installed with alternating tooth styles When replacing teeth we recommend maintaining this alternating assembly c Check for any loose hardware and...

Page 8: ...8 PARTS DIAGRAM EXPLODED VIEW...

Page 9: ...9...

Page 10: ...10...

Page 11: ...causes of action present or future whether the same be known or unknown anticipated or unanticipated resulting from or arising out of the use of said equipment This equipment must be used with care by...