1-03-2022
N
L
120 cm
Ø21 cm
4. Connect
120 cm
Ø21 cm
4. Connect
Strato excl cable
1. Drilling
Drill or dig holes in the ground.
2. Place
Place the Strato in the hole.
3. Digging
-Dig out to 40cm deep.
Make sure there is no voltage on
the ground cables
- Place the ground cables.
- Feed the cables through the
Strato.
5. Finishing
- Straighten the pole with
the help of a spirit level.
- Close the hole
in the ground.
Strato incl cable
3. Digging
-Dig out to 40cm deep.
Make sure there is no voltage
on the ground cables
-Place the ground cables
2. Place
Place the Strato in the hole.
1. Drilling
Drill or dig holes in the ground.
5. Finishing
-Straighten the pole with
the help of a spirit level.
-Close the hole
in the ground.
Connect
with an IP68
Castjoint
ground cable
Stainless steel cap
Driver
ground cable