RSS Transmitter with Pure Signal Technology (PST) - Quick Start Guide

Pg 3 of 3

7. Your Customer Service Contact

United States (HQ):

Tigo Energy, Inc.

655 Campbell Technology Pkwy
Campbell, CA 95008

EMEA Office:

Tigo Energy Italy

Srl Via Calamandrei 36 52025
Montevarchi Tuscany, Italy

Americas: +1 408 402 0802
International: 00800 2255 8446

https://support.tigoenergy.com/

LED Status

Description

Action

Red ON, Green Flashing

Leader (transmitter 1)

None; normal operation

Red OFF, Green flashing

Follower (transmitters 2-10)

None, normal operation

Red ON, Green OFF

Error, not transmitting signal

Remove power from all transmitters.
Verify all wiring is correct. Verify torque.

5. LED Status

Issue

Check

Low string voltage

The TS4-A-F produces 0.6V per unit when the RSS Signal is not present. If the string Voc
is abnormally low (<100 volts), verify each RSSx has power and that the IN and OUT
connections are correct (if using multiple RSSx), and that the Cores are properly installed.

Lower voltage than expected

One or more TS4s may not be connected properly. Use the

RSS Signal Detector

(not included) to verify the TS4 is receiving the keep alive signal.

No output voltage at the string

Verify all TS4s are connected to the modules and that all TS4s are connected to each
other.

6. Troubleshooting

!

CAUTION – For personal safety always wear and use appropriate PPE.

3. Pre-Power Checklist

Check Item

Acceptance Criteria

TS4 Installation

All PV modules are connected to a TS4-A-F/TS4-A-2F.

Core directionality

All Cores are facing the correct position (Black side towards the PV array).

Conductor signaling

Only the negative conductors are run through the RSS cores and no more than 10
conductors per Core.

Distance

The total round-trip distance of the PV conductors is <300m or <500m if Cores are
installed in series on the same strings for long distance applications.

Series transmitter wiring The transmitters are wired correctly and connections are secure.

Power supply

Power supply is wired correctly, and connections are secure.

Conduit connections

All conduit attachments are sealed and bonded, where necessary.

Workmanship

Cable ties are secured evenly, have no sharp edges, the enclosure and installation
area are left clean and accessible.

Voltage check

Check string voltage prior to powering up the system. Without the keep alive signal
the string voltage should equal 0.6V x # of PV modules in the string.

4. Commissioning

1.

Follow the normal commissioning steps of the inverter(s) installed. Note - the RSS Transmitter must be
connected to the same AC branch circuit as the inverter to meet NEC 690.12 Rapid Shutdown requirements. By
connecting the inverter(s) to the grid, power is supplied to the RSS transmitter, turning it on.

2.

The RSS Transmitter should now be powered and signaling the array to pass energy. Each string should now
have full voltage to the inverter.

!

CAUTION – For personal safety always wear and use appropriate PPE.