SME2-IS fault detector are designed in conformity with 

ENEL GSTP011 (Protection and control devi-

ce for MV substation – RGDM control unit)

; they are installed in remote-controlled Secondary Sta-

tions to detect phase-phase and phase-ground fault both on neutral compensated and both neutral 

isolated with no need of modification switching from a configuration to the other regardless of the 

feeding directions.

In particular they allow to:

• detect the presence of multi-phase and phase to ground fault,

• detect the loss of voltage on the line,

• measure the voltage and active and reactive power on MV line,

• operate in case of fault or on remote control from the UP, opening or closing of DY800

• Interface with generators present on the MV line to coordinate voltage regulation along line and 

remote trip signals.

Input circuits are suitable to acquire measurements using integrated current-voltage phase sensors; 

device can acquire, using a software switch, current measurements inputs using active sensors 

(signal is proportional to the current detected by sensor) or passive sensors (

DJ 5400 

GSTC005 

- signal proportional to the value of current derivative against time); the device allows current and 

voltage measurements using IEC 61869-10 and IEC 61869-11 Low Power sensors.

Omopolar value are obtained through vectorial calculation of current and phase voltage measure-

ments. Two communication Ethernet ports are available, one of them with IEC61850 protocol.

To assure full compatibility with RTU already existing on secondary installations, SME2-IS is equip-

ped with double interface, able to communicate both with UP (DX1215) and with future communica-

tion devices.

Settings, reading measurements and reading of fault recordings can be made using a PC or using 

the Ethernet port together with software Thysetter, freely available; all these operations can be made 

even using front panel (MMI).

In this manual there are instructions needed to mount, settings and commissioning.

Thytronic keeps the right to improve the product without further notice.

Compliance

This device comply with EU directives about:

• EMC directive: 

2014/30/EC

• LV directive:   

2014/35/EC

Technical support

Contacts: THYTRONIC Technical service 

www.thytronic.it

Copyright

All rights reserved; it is forbidden to copy documents without permission of Thytronic, as well as 

copy or modify firmware and relative software.

Warranty

The product is under one year warranty.

Summary of Contents for SME2-IS

Page 1: ...passive sensors DJ 5400 e GSTC005 signal proportional to the value of current derivative against time the device allows current and voltage measurements using IEC 61869 10 and IEC 61869 11 Low Power s...

Page 2: ...ts that can be live under fault conditions The in sulation distances are adequate to ensure the insulation seal the dielectric strength tests were per formed with respect to the housing Protection ear...

Page 3: ...rve the phase to phase direction L1 L2 L3 Select the type of sensor by setting the respective parameters in the menu Set Sensor selection SP for passive sensors CVS for active electronic sensors Conne...

Page 4: ...ENTION MBTERMINAL BLOCK COMTS 24VDC TS 51A TS V M1 TS 67AV M2 UD D A COM UD 24VDC 24Vcc 1 2 3 4 5 6 7 8 9 10 MITERMINAL BLOCK M M A L A M M ccx 89 cax 89 TC CCX TC CAX 1 2 3 4 5 6 7 8 9 10 K4 K5 K1 K2...

Page 5: ...gs and commissioning Settings of protection function can be made Using a Personal Computer with ThyVisor software installed Locally using keyboard and display MMI The ThyVisor sw is a viewer and confi...

Page 6: ...ible to cyclically browse through the menu options CLOCK ADJUST READ SET COMMUNICATION TEST Having identified the sub menu of interest it is possible to gain access by using the Right and then analogo...

Page 7: ...NERGIZED Mode NO LATCHED Min pulse width tTR1 150 ms Press the button Enter for few seconds lthe modifi cation in progress status is highlighted by the both LED51 51N e 67N Move the cursor over the pa...

Page 8: ...azza Mistral 7 Tel 39 02 574 957 01 ra Fax 39 02 574 037 63 Stabilimento 35127 Padova Z I Sud Via dell Artigianato 26 Tel 39 049 894 770 1 ra Fax 39 049 870 139 0 www thytronic it www thytronic com th...

Reviews: