background image

 

 

ICE RINK DEFOGGER

Allow a minimum of four feet clearance from any 
obstruction on the return side of the unit. 
 
Check that the unit will not block the view if the ice 
rink has a spectator area. The unit can be moved as 
long as the discharge location is not affected. 
 
Use anti-vibration pads such as machinery cork or 
rubber pads to isolate the unit from the supportive 
structure. The units are normally installed on 
platforms (see drawing). DO NOT mount units on 
plywood sheets or similar materials, which are 
prone to cause resonance. 

 

Step 3 
Condensate Drain 

The unit has a 1-1/4" MPT drain connection. The 
drain line and external P-TRAP must be heated if 
the machine is to operate at temperature below 
freezing. 

 
Step 4 
Electrical Hook-up 

Provide and install a main disconnect switch within 
the vicinity of the unit. Refer to the unit nameplate 
for proper voltage, ampacity and maximum main 
fuse protection. Wires and main disconnect switch 
should be provided in accordance with local 
electrical codes. Use copper conductors only. 
Power leads are brought into the unit through the 
top or bottom of the main control panel. Supply 
voltage must not vary more than 10% of the 
nameplate voltage. Unbalanced phase voltage must 
not exceed 2% between phases. Ensure that the 
unit is connected to the ground lug terminal, located 
in the control panel. 
 
The unit is controlled by a humidistat (factory 
installed). Control voltage is 240 volts. If a remote 
on/off switch (supplied by others) is installed, mount 
the on/off switch in a convenient location using 
wiring according to the local electrical codes. The 
switch provided should be a double pole switch, so 
that two units can use the same switch. 
 

Step 5 
Discharge Duct Extension

 

Provide a 36 inch (0.9 m) discharge duct extension 
complete with horizontally and vertically adjustable 
louvers. 

 
IMPORTANT!!! 
Before starting up the IRD, enclosure 
temperature must be between 30°F and 80°F (-
1°C and 27°C). 
 

 
 
Step 6 

Leak test the entire unit. Abnormal transportation 
and handling shocks may have caused a refrigerant 
leak. In case of solder repair use an inert gas to 
prevent scale formation in tubing. 
 

Step 7 

Wire connections may become dislodged or 
loosened during shipment. Check screws for 
tightness. 
 

Step 8 

Check drain connection. Test condensate drain by 
pouring water into the drip pan. This will also fill P-
trap. The access panel must be removed for this 
procedure. 
 

Step 9 

Check to see that clean filters are installed. If filters 
are dirty, check coils. Dirty coils must be cleaned 
and filters replaced. 
 

Step 10 

Move on/off switch on the unit to the OFF position. 
 

Step 11 

Check line voltage to match with unit nameplate. 
Install line voltage disconnect switch (see field 
wiring diagram). Connect power supply. Check 
ground connections. 
 

Step 12 

Wire the remote manual on/off switch to the 
terminals on the panel and move switch to OFF 
position. 
 

Step 13 

Turn the power on. For compressors without service 
valves the crankcase heater must be energised at 
least one hour before start-up. The crankcase 
heaters are energised as soon as power is supplied 
to the unit (if so equipped). 
 

Step 14 

Move unit on/off switch to the ON position. Move the 
remote on/off switch to the ON position. 
 

Step 15 

After the initial time delay, the compressor and 
blower will start. Control light indicates compressor 
in operation. If the compressor does not start 
(locked rotor) or knocks during start-up, stop the 
compressor and leave the crankcase heater on for 
at least 12 hours before attempting start-up again. 

Summary of Contents for IRD R404A Series

Page 1: ...om the ice surface then the horizontal duct louvers by others must be adjusted to direct the airflow away from the ice surface It is mandatory that this unit have a 36 inch 0 9 m discharge duct comple...

Page 2: ...refrigerant charge 3 Defective hot gas valve 4 Defective de ice control Refer to piping diagram for gas flow Fig 5 The installation of one or even two IRD Series units may not be sufficient to elimin...

Page 3: ...its can use the same switch Step 5 Discharge Duct Extension Provide a 36 inch 0 9 m discharge duct extension complete with horizontally and vertically adjustable louvers IMPORTANT Before starting up t...

Page 4: ...y during the active period or whenever high humidity is a problem When the return air temperature is low the IRD Series actually freezes moisture out of the air The coils have been designed for frost...

Page 5: ...ation at air inlet Follow duct design standards Unit undersized Recheck load calculations High head pressure Do not operate unit above 80 F 27 C Low airflow adjust blower belts Restricted filter dryer...

Page 6: ...Direct the airflow along the boards do not direct air over the ice surface 2 Discharge duct equipped with horizontally and vertically adjustable louvers supplied by others 3 Minimum horizontal distanc...

Page 7: ...ICE RINK DEFOGGER ELECTRICAL DIAGRAM Fig 4...

Page 8: ...MAN IRD 012 05 E 8 PIPING DIAGRAM Fig 5...

Page 9: ...ns checked for tightness Air flow and blower speed adjusted Units level and vibration isolated Drain connection tested and P trap filled Air entering temperature ____ F Minimum 4 feet Clearance on ret...

Reviews: