10.
Install power cable (if necessary).
11.
Install quick mount terminal blocks and tighten
screws (if necessary). Complete system wiring.
Tightening
torque 1.5 Nm–1.8 Nm (1.1 ft-lb–1.3
ft-lb).
12.
Install junction box lid and twist hand tight.
Insert screwdriver into ratchet slots located on
side of junction box base.
13.
Use screwdriver to ratchet on junction box lid.
Lid will rotate 30 degrees. Lid latch mechanism
fully engaged. To remove lid, repeat steps 12
and 13 but in the opposite direction.
Locate bus connection (HPT and FP only) and cable
as shown. Cut end of cable at angle to aid in piercing
grommet. Leave additional cable for expansion loop.
Two Cable Layout Tips
Insert two cables into expediter.
Note: For HPT and FP cable, exchange grommet in
Terminator with GRW-G provided in PETK-3.
Power Connection (1 to 2 Heating Cables)
Wiring Details
End Termination (1 Heating Cable Only)
Ground
Power Supply
Ground
L2 or N
L1
Ground
Form PN50848-0519
Terminator
TM
ZL
INSTALLATION PROCEDURES