4
12.
For power connection applications: Use
dimple molded into side of junction box base
to locate center hole, drill for user supplied
power connection fitting per manufacture’s
recommendations.
13.
Mount junction box on expediter making sure
to align slots to properly orient junction box
base.
Dimple for Center Line
Drilled thru (1) Wall
14.
Install quick mount terminal blocks twist to
position and tighten screws.
6.
Cut splice cover top and splice cover bottom to
match outside diameter of tubing bundle.
7.
Mount expediter base with o-ring to splice
cover bottom using (3) M5 mounting screws
and lock washers. Punch out weep hole.
O-Ring
Splice Cover
Bottom
Expediter Base
Weep
Hole
9.
Assemble splice cover top, tubing bundle, and
splice cover bottom together as shown Snap
together firmly. Inspect ends of tubing splice
cover for snug fit. Apply additional RTV sealant
where needed.
Align Slot
Terminal Blocks
(Typical)
Terminator DP/FAK-2 and FAK-2L
Cut and Remove
Ends to Fit
TubeTrace
Tubing Bundle
Field Drilled
(By Others)
8.
Install the Silicone Gasket (cut off excess). Apply
RTV Sealant to both halves.
RTV
Sealant
Splice Cover Top
RTV Silicone
Gasket
Splice Cover
Bottom
10.
Apply self-vulcanizing tape around bundle jacket
and work up over FAK ends.
11.
Terminate heat tracing with appropriate PETK
termination kit. Refer to PETK installation
instructions (purchased separately) for details
not addressed here.
Power Connection
Boot
Ground Braid
Heat Tracing
Conduit and Wire (By Others
For Power Connection Applications)