Consumables
Cooling Water
5-2
iCAP Qnova Series ICP-MS Pre-Installation Requirements Guide (P/N BRE0006946, Revision A)
Thermo Scientific
Cooling Water
For operation of the iCAP Qnova Series instruments, cooling of some
components, like the interface and the RF generator, is required.
The water used for the coolant set up should be free of suspended matter
to avoid clogging of the cooling circuit. An in-line filter is supplied with
the instrument to guarantee consistent water quality. See
the cooling water specifications.
The water temperature should be in the range specified in
Lower temperatures could lead to a condensation of atmospheric water
vapor.
A water hose (black) with an OD of 12 mm (ID 8 mm) and a length of
10 m is delivered with the instrument. The cooling water connections to
the instrument are shown in
Table 5-1.
Cooling water specifications
Cooling Water Specifications
Values
Supply Rate
> 5.5 L/min
Temperature
20 to 30 °C, optimum at 21 °C
Pressure
0.25 to 0.6 MPa (2.5 to 6 bar)
pH
6-8
Recommended
conductivity
< 1000 μS/cm
Solid Residual
< 50 μm particle size
NOTICE
Make sure the specifications in
are met when connecting the
instrument to an inhouse water supply.
Summary of Contents for iCAP Qnova Series
Page 1: ...iCAP Qnova Series ICP MS Pre Installation Requirements Guide BRE0006946 Revision B April 2018 ...
Page 2: ......
Page 3: ...BRE0006946 Revision B April 2018 iCAP Qnova Series ICP MS Pre Installation Requirements Guide ...
Page 92: ......
Page 93: ......
Page 94: ......