Doc. 065250-06 03/2020
85
7 • Startup, Operation, and Shutdown
7.1
Initial Startup Checklist
Complete the following installation steps before operating the Dionex Integral
system for the first time.
7.1.1
Prepare the Site and Facilities
1. At the installation site, select the location for the Dionex Integral
system components (chromatography system modules, SP, and SS).
Refer to
Installation Requirements and Customer Responsibilities:
Process Analytical Systems
(Document No. 070186) for appropriate
locations and distances.
2. Provide the facilities specified in the installation requirements
document. Also refer to this document for appropriate voltages,
currents, pressures, and flow rates.
7.1.2
Connect the Facilities
1. Connect electrical power to the Dionex Integral system components
and the computer. A power cord is provided with each component. If
the Dionex Integral system includes an AE, the wall receptacle must
be a NEMA L5-20R receptacle.
2. Confirm that LE regulators are turned down and that valves are
turned to the
VENT
position. Connect gas sources to the system
components. Close the shutoff valve for each of the gas inlets.
3. Connect water sources to each system. Close the shutoff valve for
each of the sample inlets.
4. Direct the waste lines into the drain. Refer to the installation
requirements document for the drain location.
Summary of Contents for Dionex
Page 12: ...Dionex Integral Systems Operator s Manual x Doc 065250 06 03 2020...
Page 17: ...1 Introduction Doc 065250 06 03 2020 5 Figure 1 2 Example Analyzer Configuration...
Page 28: ...Dionex Integral Systems Operator s Manual 16 Doc 065250 06 03 2020...
Page 72: ...Dionex Integral Systems Operator s Manual 60 Doc 065250 06 03 2020...
Page 92: ...Dionex Integral Systems Operator s Manual 80 Doc 065250 06 03 2020...
Page 96: ...Dionex Integral Systems Operator s Manual 84 Doc 065250 06 03 2020...
Page 154: ...Dionex Integral Systems Operator s Manual 142 Doc 065250 06 03 2020...
Page 160: ...Dionex Integral Systems Operator s Manual 148 Doc 065250 06 03 2020...
Page 202: ...Dionex Integral Systems Operator s Manual 190 Doc 065250 06 03 2020...
Page 214: ...Dionex Integral Systems Operator s Manual 202 Doc 065250 06 03 2020...
Page 228: ...Dionex Integral Systems Operator s Manual Index 10 Doc 065250 06 03 2020...