4 • Troubleshooting
Doc. 031857-03 4/06
4-19
•
Clogged column bed supports
Refer to the instructions in the column manual for troubleshooting guidance.
Column manuals are included on the Dionex Reference Library CD-ROM
(P/N 053891).
•
Contaminated columns
Clean the columns as instructed in the column manual.
•
Plugged injection valve passages
Rebuild the injection valve (see
4.8
Peak “Ghosting”
“Ghosting” is the appearance of extraneous peaks in a chromatogram. These may
be late-eluting peaks from a previous injection, or they may be the result of a
contaminated standard or eluent, or a malfunctioning injection valve. These peaks
may co-elute with peaks of interest, resulting in nonreproducible peak
heights/areas.
•
Insufficient time between sample injections
Wait until the previous sample has been completely eluted before making
another injection.
•
Insufficient flush between samples
Flush the sample loop with at least 10 loop volumes of deionized water or
sample between sample injections.
•
Incorrect or contaminated standards
Remake standards.
•
Incorrect or contaminated eluent
Verify that the correct eluent concentration is selected.
Install or replace the end-line filter on the end of the deionized water line (see
•
Malfunctioning injection valve
1. Rebuild the injection valve (see
2. If the valve leak persists, contact Dionex for assistance.
Summary of Contents for Dionex ICS-2000
Page 1: ...ICS 2000 ION CHROMATOGRAPHY SYSTEM OPERATOR S MANUAL Document No 031857 Revision 03 April 2006...
Page 64: ...ICS 2000 Ion Chromatography System 2 44 Doc 031857 03 4 06...
Page 204: ...ICS 2000 Ion Chromatography System A 6 Doc 031857 03 4 06...
Page 366: ...ICS 2000 Ion Chromatography System D 12 Doc 031857 03 4 06...
Page 372: ...ICS 2000 Ion Chromatography System F 4 Doc 031857 03 4 06...
Page 378: ...ICS 2000 Ion Chromatography System G 6 Doc 031857 03 4 06...