IOM CRUZcontrol®
P/N: 90480009
Revision Date: 03/18/2019
Page
11
of
58
Conveyor Flow
(Some conveyor configurations will result in the conveyor flow direction being reverse from what
is shown in the illustration. In those situations, the Interconnection Cables are routed in reverse
from that shown.)
CRUZcontrol On Site Installation
Installation will consist of the following:
•
Connection of Air Supply air tubing between conveyor beds, closing and terminating the
ends of the Air Supply tubing, and providing the air supply to the conveyor.
•
Connection of the Logic Assembly interconnection cables from the last zone of a conveyor
bed to the first zone in the next upstream conveyor bed.
•
Providing a suitable 24 VDC power supply and connecting it into the string of Logic
Assemblies.
•
Providing a Singulation Release signal for the discharge zone (using Function Module).
•
Providing a Slug Release signal for the discharge zone, if required (using Function
Module).
•
Obtaining Zone Status indications as required for system control (using Function Module).
•
Terminating unconnected M12 cable ends with Termination Plugs. This is suggested to
protect the cable ends from damage.
•
Adding auxiliary photoelectric sensors as required for discharge and full line condition
sensing.
TGW Systems Part No.
Description
90139992
Male M12 Termination Plug (use for terminating male cable
ends)
90139994
Female M12 Termination Plug (use for terminating female
cable ends)
Photoelectric
Sensor
Logic
Module
Air Supply
Air Supply
Zone Control
Air
Zone Control
Air
Logic Assembly
Interconnection Cable from
downstream zone
(Shown disconnected from
Logic Module Assembly)
Logic Assembly
Interconnection
Cable to upstream
zone.