IMPORTANT SAFETY INFORMATION LISTED ON REVERSE

READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS

DATE

12-18-17

40429 Brickyard Drive • Madera, CA 93636 • USA

559.438.5800 • FAX 559.438.5900 

www.tekaillumination.com • [email protected]

REFERENCE NUMBER

INS-2572-00

TOWER BOLLARD™ (TWB)

Max. 3/4”

1.  Adjusted anchor bolts to project no more than 

3/4” above the anchor plate after installation. The 

three (3) 1/4-20 nuts on top of the plate may be 

left in place while concrete is poured.

Finished grade

Finished grade

Finished grade

3.  With the conduits in place and the anchor 

plate properly positioned, secured and leveled, 

concrete may be poured.

Finished grade

Finished grade

Finished grade

2.  Install anchor plate and bolt assembly flush 

with the finished grade. Run conduit inside 

of the anchor plate center hole prior to 

pouring concrete. The conduit may project 

above the finished surface of the concrete 

by 3/4” maximum. Max of four (4) 3/4” trade 

size conduits may be positioned inside anchor 

plate center hole prior to concrete pour.

Anchor #36 Installation

4.  The fixture may be installed by removing the 

three (3) 1/4-20 nuts and re-using them with 

wrench to secure the fixture mounting base 

assembly. See fixture installation sheet(s) for 

additional information.

 

Soil Prep

Conduit
trench

B.  Dig hole 10” wide and 24” deep.

Conduit

Trench

Excavated 

for Anchor Kit

C.  Prep soil according to DIG-IT Guide.

A.  Determine Soil Type by referencing DIG-IT Guide. 

Prep soil according to DIG-IT Guide.