8
T119DIN
PROGRAMMING
STEP
ACTION
EFFECT
1
Turn on the unit
the green LED lights up
2
Push TEST twice in sequence
the red PRG LED flashes
3
Push TEST within 5" without releasing it until the
PRG LED is ON
the PRG LED is ON continuously
4
Push TEST within 5" to select the desired FAN
time
the red LED switches from
T1-T2-T3-T4
(FAN time 5’-10’-20’-40’)
5
Stop pressing TEST when the LED is on the Tx
corresponding to the desired time. Wait for all the
LEDs to go OFF.
6
End of programming
all the LEDs are switched OFF
7
Turn the unit off and then back on
FAN PROGRAMMING CYCLE
To choose the FAN time (point 4):
Press TEST once to select
5'
(T1 ON)
Press TEST twice to select
10'
(T2 ON)
Press TEST three times to select
20'
(T3 ON)
Press TEST four times to select
40'
(T4 ON)
If you don’t need any FAN cycle,
push TEST 5 times (all LEDs are OFF). The unit is programmed only for ALL1 and
ALL2 (alarm and trip)
ALARM RELAY TEST
STEP
ACTION
EFFECT
1
Push TEST three times in sequence
the T1,2,3,4 LEDs light up in
sequence
2
Within 5” push TEST without releasing it until the
LEDs light up all together
LEDs T1,2,3,4 flash all together
3
After 5” the relay FAN lights up, followed by the
ALL1 and ALL2 relays
the LEDs and relays of FAN 1-
ALL1-ALL2 are ON
4
END OF THE TEST CYCLE
all the red LEDs go OFF
Summary of Contents for T119 DIN
Page 1: ......