t.a.c. Satchwell SVT Quick Start Manual Download Page 3

INSTALLATION

FLUSH PANEL MOUNTING

1.

Select location which is reasonably clean and dry, with adequate 
access. Ambient limits 0 to 40°C.

2.

Remove fascia cover (Fig.4) using the key supplied (Fig.2).

3.

Rotate locking screws through a quarter turn and separate 
controller sections (Fig.5).

4.

Unplug ribbon cable by pressing outwards the side locking wings 
(Fig.6). (If flush mounted, omit steps 5 to 8 and proceed to 9).

WALL MOUNTING (or Rear Panel Mounting)

5.

Remove conduit cut-outs as required with a sharp knife. Screw 
back section to wall (Fig.7). When trunking is used the controller 
must be mounted using 32mm spacer bushes.

6.

Connect wiring in accordance with appropriate scheme diagram. 
Observe wiring precautions given in table on Page 8.

7.

Move slide switch 'S' to correct position for the application (see 
Commissioning, Fig.16).

8.

Reassemble controller by plugging ribbon cable back into socket 
on rear power board. Take care to align plug and socket the right 
way round - DO NOT FORCE. Push controller case onto base 
section, locating the two guide rods into the bushes and turn 
screws to relock (Fig.8).

FLUSH PANEL MOUNTING

9.

Move slide switch 'S' to correct position for the application (see 
Commissioning, Fig.16).

10. Remove power board from the base section by undoing two front 

screws 'A' (discard) and two rear screws 'B' which mount the 
bushes (Fig.9).

11. Refit the two bushes into base section with screws 'B' (Fig.10).

12. Place the two hexagonal space bushes 'C' (supplied) over the 

locking rods in front part of controller (Fig.11).

13. Carefully fold the ribbon cable as shown (Fig.12). Reposition the 

power board over the ribbon cable (board points to rear when 
assembled) using the two screws/washers 'D' supplied (Fig.13).

14. Fit controller into panel cut-out (138 x 138mm) and secure using 

brackets/screws provided (Fig.14).

15. Wire up as step 6 and remove conduit cut-outs from base section, 

see step 5.

16. Plug ribbon cable back into socket. Observe right way round - DO 

NOT FORCE. Refit back of controller, locating the two bushes on 
the guide rods and turn screws to relock (Fig.15).

Caution
Do not switch on mains power until commissioning checks 1 to 8 
have been carried out.

COMMISSIONING

SYSTEM CHECK

1.

Check that all equipment is correctly located and fitted.

2.

Remove controller from back section (see Installation 2, 3 and 4).

3.

Check all control circuit wiring.

a.

Ensure there is no mains on low voltage (upper) terminals.

b.

Check all wires are in accordance with scheme diagram or 
diagrams on this leaflet.

c.

Ensure all necessary links and resistors have been connected 
or removed as instructed.

4.

Check slide switch 'S' is in correct position for application.

5.

Temporarily remove sensor wires and substitute a simulator. If not 
available, connect a variable resistor, or switchable fixed resistors 
of values approximately 2200 Ohms, 1800 Ohms and 1500 Ohms.

6.

Rotate D.P.H. selector switch to fast run position 'T'.

7.

Reassemble case, plugging in (ribbon cable) if unplugged.

8.

Set Td to 20°C, Tn to 10°C, and override switch to Auto

 . If a 

simulator is used, set this to 16°C. Otherwise select the 1800 Ohm 
resistance to simulate this value.

9.

Switch on power supply and set the clock as detailed in 'SETTING 
THE CLOCK'.

10. Override time switch ON then OFF. See dialogue or digital clock 

setting instructions for details.

11. Plant and R2 relays should now be 'Off'. (Neither LED illuminated).

12. Override time switch 'On'. After approximately 15 seconds the 

'Plant' relay should energise and after a further 15 seconds relay 
R2, when slide switch 'S' is in position 'A'. (Both LEDs illuminated).

13. This test simulates a 'Fast Run' optimum start period of 2 hours 

speeded up to 30 seconds with a plant switch-on half way through 
this period because the simulated inside temperature of 16°C is 
half way between 12°C (max. preheat) and 20°C (zero preheat). 
Boost is terminated when the relay R2 is energised at the end of 
this period.

14. Override time switch to 'Off' position. Both plant and R2 relays 

should de-energise. (Both LEDs off).

15. Set simulator above 20°C or select the 1500 Ohms resistance. 

Relay R2 should energise (

LED illuminated).

16. Set simulator below 10°C or select the 2200 Ohm resistance. The 

'Plant' relay should energise (

LED illuminated). This test is to 

check frost protection.

17. Switch off power supply. Open case. Remove simulator or 

resistances. Reconnect room sensor wires. Reassemble case. 
Switch on power supply.

18. Set time switch and parameters as following section.

WALL MOUNTING

Fig.4 

Fig.5 

Fig.6 

Fig.7 

Fig.8 

Fig.9 

Fig.10 

Fig.11 

Fig.12 

Fig.13 

Fig.14 

Fig.15 

Position 'A' gives termination of boost on relay R2, 
for use on applications involving day control from a 
compensator or other Satchwell controllers (see 
connection diagrams Fig.4 and Fig.5).

Position 'B' gives a single pole change-over output 
from relay R2 for day control of pump/boiler and/or 
motorised valve (see connection diagrams Fig.6, 
Fig.7 and Fig.8).

Slide 
switch 'S'

Fig.16 

Slide switch 'S' on circuit 
board inside front portion 
of controller

Summary of Contents for Satchwell SVT

Page 1: ...regain the required temperature at occupancy time In very mild weather this delay can be as much as five hours later than in cold weather and fuel savings of between 10 and 25 are possible By relating the start time to the inside temperature rather than the outside temperature the insulation and thermal mass of the building are taken into account The SVT makes the benefits of optimum start control...

Page 2: ...hort power interruption to the electronics during the preheat period Ambient Temperature Limits Operating 0 to 40 C SVT 4201 Storage Transit 0 to 55 C 0 to 50 C SVT 4251 Max Ambient Humidity 95 rh non condensing CONSTRUCTION DIN Standard 144 x 144mm square for wall or flush panel mounting cut out size 138 x 138mm Case 2 piece polycarbonate or ABS moulding Fire Resistant Protection Class IP 41 Wind...

Page 3: ... upper terminals b Check all wires are in accordance with scheme diagram or diagrams on this leaflet c Ensure all necessary links and resistors have been connected or removed as instructed 4 Check slide switch S is in correct position for application 5 Temporarily remove sensor wires and substitute a simulator If not available connect a variable resistor or switchable fixed resistors of values app...

Page 4: ...l override switch has the following functions I OFF Automatic control II ON Overrides are usually set from the SVT and the clock override is left in the Automatic position SETTING THE ANALOGUE SWITCHING TIMES 1 Set the required weekly programme by pushing in the blue segments around the clock dial for all ON periods and pulling them out for all OFF periods 2 For omitted days such as Sunday all the...

Page 5: ...WI SET WI MONTH SET WI MONTH SET WI YEAR TIME DATE SU WI SET SU WI SET SU WI SET DAY SU SET SU DAY SET SU MONTH SET SU MONTH SET SU YEAR SET SU YEAR SU TEST MODIFY NEW PROG MODE SET TIME DATE SU WI PROG MODE SET Programming One program switch on time switch off time switch on and switch off days Programs with predefined switch on switch off days DAY 1 7 MO SU DAY 1 5 MO FR DAY 6 7 SA and SU ...

Page 6: ...1 3 2 4 5 NEW ON OFF PROG 6 7 TEST MODIFY NEW PROG NEW PROG 1 3 2 4 5 NEW PROG 6 7 1 3 2 4 5 NEW PROG 6 7 DAY 1 7 1 5 6 7 ANY DAY NEW PROG 1 3 2 4 5 NEW ON OFF PROG 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 Select switch on day Tuesday Select switch off day Tuesday 5x ...

Page 7: ...t program Change switching times Change switching days MODIFY PROG MODIFY PROG MODIFY PROG Prog 1 Prog 2 Prog 3 NEW PROG 1 3 2 4 5 MODIFY ON OFF PROG 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 1 3 2 4 5 ON OFF 6 7 5x DEL ONE Delete a single program DEL ALL Delete the programs for the channel TEST MODIFY NEW PROG MODIFY PROG MODIFY PROG MODIFY PROG 1 3 2...

Page 8: ...parate loom or trunk from any mains wiring and spaced as far as possible away from it 230Vac 45cm Min 415Vac 58cm Min both voltages are with respect to earth and a maximum current of 15A For other voltages currents refer to the IEE report titled Electro magnetic interference September 1987 ISBN85296353X TEST MODIFY NEW PROG TEST PROG PROG C1 TEST prog Programs in the order entered SERIAL Switching...

Page 9: ...4 at switch off time after inside temperature cools to below Td R2 makes 5 3 if inside temperature Td R2 makes 5 4 if inside temperature Td nominal differential 1 C 1 2 PLANT Boiler Pump 3 DAY 4 BOOST 5 COMMON Fig 1 Voltage free outputs WIRING PRECAUTIONS Fig 2 The switch takes effect at the next switch on time HOLIDAY Open AUTO Closed Remove link 6 7 Fig 3 RECORDER 0 to 10Vdc RECORDER 0 to 100mV ...

Page 10: ...mmissioning procedures have been completed If any equipment covers have to be removed during the installation of this equipment ensure that they are refitted after installation to comply with UL and CE safety requirements This is a mains operated device Local wiring regulations and usual safety precautions must be observed Note Earthing requirements Do not switch on mains power until commissioning...

Reviews: