INSTALLATION 

GOLDen GATE, TBLZ-1/2-1-3-41

1. General

Kommunikationsenhet TBLZ-1/2-1-3-41 är avsedd att 
användas till luftbehandlingsaggregat GOLD version 4, A 
och B.
Enheten består av:

1.

  4-modulers normkapsling för din-skenemontage IP20.

2.

  9-pol d-subkontakt för anslutning via seriekabel till

  GOLD eller modem.

3.

  Plint för kraftmatning 9-24 V AC/DC, 165 mA vid 12V.

4.

  RJ-45 kontakt för Ethernetanslutning.

5. 

 Plint för två digitala ingångar. 

Other features:

Module LED.
RX LED.
Link LED.
GOLD Comm. LED.

2. Safety Precautions

Be careful whenever you do any wiring to the unit.Never 
carry out any work on the unit while the power supply is 
switched on. Doing so could harm you and damage the 
unit. 
Observe local electrical safety regulations as you install the 
unit.

3. Installation

3.1 General

Connect conductors to the V in+ and V in- terminals (see 
Fig. 1) of the GOLDen GATE unit and wire them to a sepa-
rate power supply unit with the correct capacity or to the 
12 V DC or 24 V AC terminals of the GOLD air handling 
unit. 

NOTE!

 The polarity G and G0 is important. 

Configure the communication unit using the configura-
tion program available from our website address: http://
www.swegon.com. Install the program according to the 
instructions in the setup window.

Fig. 1

3

2

1

4

5

Summary of Contents for GOLDen GATE

Page 1: ...GOLD Comm LED 2 Safety Precautions Be careful whenever you do any wiring to the unit Never carry out any work on the unit while the power supply is switched on Doing so could harm you and damage the unit Observe local electrical safety regulations as you install the unit 3 Installation 3 1 General Connect conductors to the V in and V in terminals see Fig 1 of the GOLDen GATE unit and wire them to ...

Page 2: ...nd enter the IP addres ses As standard admin is used both as the user name and the password see Fig 4 The unit can be configured via our integrated webpage for both mail master and PPP function with links to other GOLDen GATE units in the same network If you know the IP address you can also configure the unit via its own built in webpage After you ve saved your settings you ll have to reboot the u...

Page 3: ...e the GOLD see Fig 6 and 7 4 Commissioning 4 1 GOLD Version 4 A Set the LON Communication to 0 in the service menu 4 2 GOLD Version B GOLD units with Program Version 1 11 DIP switch 3 must be in the ON position and DIP switch 4 in the OFF position on the GOLD AHU control unit see Fig 7 GOLD units with Program Version 1 12 and better DIPs witch 3 must be in the OFF position and DIP switch 4 must be...

Page 4: ...ergized LED flashes green while configuration is in progress LED flashes red if the memory malfunctions LED shines red in the event of a serious fault in the hardware GOLD Comm LED fl ashes green while communication between the GOLD and the GOLDen GATE is in progress LED shines red if an error in communication occurs between the GOLD and the GOLDen GATE LED is not lit while there is no traffi c be...

Reviews: