Swegon ADAPT Colibri c Installation, Commissioning Maintenance Download Page 3

3

Swegon reserves the right to alter specifications. 

20120717 

www.swegon.com

WISE

 

Electrical connections.

All the connections are wired to the CONNECT Adapt junc-
tion box. From there, the Master air diffuser is connected 
by means of the LINK Adapt (RJ45) cable included in the 
delivery. The slave air diffusers, if required, are connected 
by means of the same type of cable to their respective slave 
contacts. If there are more than 2 slave air diffusers, a SPLIT 
Link Adapt should be used for further connection to the last 
slave air diffuser. See Figure 7. If SPLIT Link Adapt is used, the 
maximum length of LINK Adapt from the junction box to 
the last air diffuser is 15 meters. If ADAPT is to be connected 
through Modbus communication, this should be done with 
the LINK Modbus (RJ12) cable. The maximum length of 
SPLIT Link Modbus is 10 meters from the junction box to 
the last air diffuser. Use double CONNECT Adapts if longer 
distances are required. All cables and contacts are different 
so that they will not be confused or incorrectly connected.

Electrical data

ADAPT is supplied with power via the junction box. See 
the wiring diagram in figure 7 or relevant diagram from the 
Swegon Templates application, containing details for the 
specific installation. It is important that cables with appro-
priate cross-sectional area, transformers of correct size and 
power supply cables of correct length are selected. This 
can for example be carried out with the dimensioning tool 
“Cable and Transformer Design”, available for download 
from www.swegon.com (the application is available in 
english and swedish language versions). 

 

Supply voltage

24 V AC ±10 % 

Max. power consumption (controller only)

3 VA

Cable rating (controller only)

0,6 A

Ambient temperature

0 °C - +50 °C

Figure 6. Air diffuser connections.

1. Connection for LINK Adapt cable (RJ45) 
2. Connection for the LINK Modbus cable (RJ12).

 

3. Direct 24 V connection if a junction box is not used and the air 
diffuser will be completely “stand alone”.

Figure 5. Commissioning with TUNE Adapt.

2

3

1

24 V

Modbus

Summary of Contents for ADAPT Colibri c

Page 1: ...rivets The diffuser should be turned so it s hinges C figure 2 face the same direction as the inlet of the commissioning box Readjust the hanger rods of the commissioning box if needed so that the air diffuser is firmly positioned against the false ceiling or the frame work of the modular suspended ceiling 3 Remove the frontplate section of the air diffuser by applying the Quick Access principle s...

Page 2: ...de the light emitting diode shines orange The different LED indications Steady green LED Normal operation the air diffuser is operating normally Flashing green LED The air diffuser has just been ener gised and calibration is in progress Steady red LED Function failure see separate docu mentation for TUNE Adapt Steady orange LED The commissioning mode max airflow Flashing orange LED Other commissio...

Page 3: ... longer distances are required All cables and contacts are different so that they will not be confused or incorrectly connected Electrical data ADAPT is supplied with power via the junction box See the wiring diagram in figure 7 or relevant diagram from the Swegon Templates application containing details for the specific installation It is important that cables with appro priate cross sectional ar...

Page 4: ...er Slave air diffusers and accessories 1 ADAPT Master air diffuser 2 ADAPT Slave air diffusers 3 CONNECT Adapt wiring terminals 4 230 24 V AC Transformer 5 LINK Adapt 5 m long RJ45 cable 6 LINK Modbus 5 m long RJ12 cable 7 DETECT Quality 3 VA or TUNE Temp 1 VA 8 ACTUATOR Radiator control max 3 valves at 6 VA 9 ADAPT Relay relay for lighting 10 Connection to main control system Modbus RTU 11 SPLIT ...

Reviews: