background image

Actionair Span Installation Guide

Installation 

Guide

Applies to...

Actionair SmokeShield PTC 

Health and safety

•  This process must be undertaken by competent per-

sons. More than one person may be required to ensure 
the safe handling of large dampers and other materi-
als. Use must be made of access equipment to ensure 

unsafe practices are not used to approach walls or diffi

-

cult access areas.

•  Standard site PPE should be used (minimum steel toe 

cap boots, hard hat); together with any protective 
eyewear, gloves and masks, when drilling or cutting is 
being undertaken. The latter should also be used when 

handing the wall construction materials, as defined by 

the material suppliers. If loud equipment is being used, 
hearing protection should be used.

•  All waste materials should be collected and disposed of 

as defined by the relevant supplier.

•  Actuators: All wiring should be carried out in accor-

dance with the wiring details provided by the IEE and 
BS regulations and by a competent person. Care must 
be taken when installing and inspecting dampers, as 
they are likely to close without warning due to loss of 
electrical power or a temperature rise in the ductwork. 
This is their prime function. Do not insert any items, 

fingers or limbs between the blades. Larger dampers 

must be handled in accordance with current regula-
tions and good practice due to weight.

Drawings

Please visit our website to download the installation 
drawings, which are located on the relevant product 
download section.

Contents

CE Installation Method Overview ..................... 2

Horioztonal Damper Installation SPAN (access side 
above) ........................................................................ 3
Horioztonal Damper Installation SPAN (access side be-
low) ............................................................................ 4

Actuators ............................................................. 5
Periodic Maintenance ......................................... 6

Wiring Diagrams ....................................................... 7
Mode 6 PTC 230V .................................................... 7
Mode 5 PTC 24V ...................................................... 7
Mode 5-3P PTC 24V ................................................. 7

SPAN Damper Dimensional Data ....................... 8
Troubleshooting .................................................. 9
Inspection and handover check sheet ............. 10
Notes .................................................................. 11

Summary of Contents for Actionair SmokeShield PTC

Page 1: ...nt supplier Actuators All wiring should be carried out in accor dance with the wiring details provided by the IEE and BS regulations and by a competent person Care must be taken when installing and inspecting dampers as they are likely to close without warning due to loss of electrical power or a temperature rise in the ductwork This is their prime function Do not insert any items fingers or limbs...

Page 2: ... with fire separating elements to maintain fire compart ments The SmokeShield is an actuated failsafe close damper with low smoke leakage often referred to in the industry as a Fire Smoke damper Under the Fire Damper Product standard BS EN 15650 our Fire Damper products are tested to BS EN 1366 2 and classified under BS EN 13501 3 For smoke control the product you use should be tested to BS EN 121...

Page 3: ...nto the interface shroud Do NOT fill above damper casing 6 When compound has fully set remove damper inter face transit plate and check the internal is free from any debris remove any debris 7 Follow the actuator installation procedure detailed in this document Comments Rev Drawn By M Bushell Approved By Kimberley M 1 Reference No Gore S Checked By AAF12368 Description If your proposed installatio...

Page 4: ...d the damper casing making sure all the gaps are fully sealed as per industry standard 8 When the first layer has set pour in the next level to 100mm thickness IMPORTANT Compound must not be too watery or runny as it risks penetrating into the interface shroud do NOT fill above damper casing against penetration of compound into interface shroud 9 When compound has fully set remove the shutterbatt ...

Page 5: ...n Both screws should be tightened fully to ensure that both sections of the ETR are closed together It is a safety feature if both sections are not closed the unit will not operate For ductless installations the ETR should be fitted onto the damper spigot not casing above the damper interface shroud and in accordance with the fitting instructions If the ETR is not fitted in the exact manner descri...

Page 6: ...s A comprehensive example of the maintenance pro cedure is given in Annex D of the standard Some automatic systems may allow more frequent testing 48hr or less and this may be required by a national standard Approved Document B Volume 2 Clause 10 12 states adequate means of access must be provided to allow inspection testing and maintenance of both fire damper and its actuating mechanism BS 9999 2...

Page 7: ...LY OPEN AC DC 230V 50 60 Hz 14 VA 12 4 W 30 C 50 C CONTINUOUS TF 72 C AC 250V 6 3 A N CONTINUITY WITH COMMON ELECTRICAL THERMAL RELEASE ETR MUST BE FITTED TO DUCTING FOR DAMPER OPERATION SPRING BIASED TEST SWITCH WHEN DAMPER CLOSED CONTINUITY WITH COMMON WHEN DAMPER OPEN CONTINUITY WITH COMMON WHEN DAMPER CLOSED CONTINUITY WITH COMMON WHEN DAMPER OPEN Supply Off Damper spring closes Mode 5 3P PTC ...

Page 8: ...H WIDTHS AND HEIGHTS OF 200 1000MM FOR DUCT WIDTHS AND HEIGHTS OF 151 199MM FOR DUCT WIDTHS 200MM 1000MM WITH HEIGHTS OF 100 199MM Base Dampers Circular Dampers Series 601 For Circular and Flat Oval Dampers spigots are 3mm under duct size Diameters and flat oval diameters in 1mm increments Circular Dampers Series 601 FOR DAMPERS 100 150MM D FOR CIRCULAR AMPERS SERIES 601 DIAMETERS 151 199MM 2 FOR ...

Page 9: ...red Check wiring in accordance with procedures The ETR cables have been damaged or tampered with Replace with new mode Control Mode operates but limited or no movement of damper blades is observed The mode is not correctly synchronised with the inter face Remove motor from interface Check motor in fully released state Set position of interface and refit motor with label upmost include motor locati...

Page 10: ...pening will invalidate the installation method Damper installer to advise the lead contractor if problems are foreseen 8 Using the access opening provided check that blades open and close Check position of damper blades 9 Has the damper been checked for internal cleanliness free from damage and that vertical casings in particular are free from debris With the damper in the closed position inspect ...

Page 11: ...11 20220811 L00009 1 2 Swegon reserves the right to alter specifications Actionair SPAN Installation Guide Notes ...

Reviews:

Related manuals for Actionair SmokeShield PTC