GENERAL
Consult this section when unpacking, inspecting,
and installing Sunnen
®
Vertical Honing Machine
(see Figure 1-1)
. Hereafter referred to as the machine.
TOOLS & MATERIALS
The following tools and materials are required for
unpacking and installing of your Machine:
Knife
Hex Wrenches
Hammer
Open End Wrenches
Crow Bar
Cleaning Solvent
Tin Snips
Screwdriver (Std)
Slip Joint Pliers
Forklift
INSTALLATION
Read the following instructions carefully and
thoroughly before unpacking, inspecting and
installing your Machine. All references to right and
left in these instructions are, unless otherwise noted,
as seen by operator as one looks at Machine or
assembly being described
(refer to Figure 1-1)
.
NOTE:
When ordering parts for, or requesting
information about your Machine, include Model and
Serial Numbers printed on Nameplate.
1. Move Machine to staging/unpacking area.
2. Remove plastic wrap.
3. Remove top and sides from packing crate.
4. Remove all loose components from crate.
5. Check all components against packing list
6. Inspect Machine and components for dents,
scratches, or damage resulting from improper han-
dling, by carrier. If damage is evident, immediately
file a claim with carrier.
CAUTION
Machine Base may be forked from any side. DO
NOT support weight of machine on bottom of
Electrical Enclosure when lifting or moving.
7. Remove Bolts securing Machine to Skid.
8. Using a forklift remove machine from skid and
move to desired location and lower into place
(see
Figure 1-2)
.
While machine is up in the air, screw in Four (4)
Corner Feet and Two (2) Center Feet.
NOTE:
Machine should be located on a leveled
concrete floor away from heavy traffic. Allow at least
1m (38in.) around enclosure to any adjacent equipment
and walls. Refer to Figure 1-A, Floor Plan Layout.
1
FIGURE 1-1, Vertical Honing Machine
FIGURE 1-2, Fork Lift
RIGHT
FRONT
LEFT
SECTION 1
INSTALLATION
R
S
V
3
R
SV-360
Summary of Contents for SV-2460
Page 14: ...8 NOTES...
Page 22: ...16 NOTES...
Page 26: ...20 NOTES...
Page 32: ...26 NOTES...
Page 36: ...30 NOTES...
Page 38: ...32 NOTES...
Page 40: ...34 NOTES...
Page 41: ...1 OF 2 C DECLARATION OF CONFORMITY 35 SAMPLE CE DOCUMENT...
Page 42: ...2 OF 2 C DECLARATION OF CONFORMITY 36 SAMPLE CE DOCUMENT...