AC Power and HVAC Service Requirements
Electrical Power Planning
2-5
If you do
not
use PDUs in the cabinet, use Tables
and
to determine the number
of AC power outlets required
outside the cabinet
.
1. In the Quantity column, write the number of each type of component.
2. Multiply the value in the Quantity column by the value in the Outlets column, and
enter the total in the Subtotal column.
3. Add the values in the Subtotal column and enter the sum next to TOTAL NUMBER
OF A-SIDE POWER OUTLETS and TOTAL NUMBER OF B-SIDE POWER
OUTLETS.
Table 2-7. Worksheet: A-Side External Power Outlet Requirements: No PDUs
Component
Quantity
Outlets
Subtotal
ftServer systems
x
1
Storage enclosures
x
1
LCD monitor units or external monitors
x
1
Tape-drive enclosure
x
1
Other peripheral components
TOTAL NUMBER OF A-SIDE POWER OUTLETS
Table 2-8. Worksheet: B-Side External Power Outlet Requirements: No PDUs
Component
Quantity
Outlets
Subtotal
ftServer systems
x
1
Storage enclosures
x
1
Other peripheral components
TOTAL NUMBER OF B-SIDE POWER OUTLETS
Summary of Contents for ftServer 2510
Page 1: ...Stratus Technologies R627 04A Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide...
Page 8: ...Tables viii Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Page 12: ...Preface xii Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Page 50: ...Planning for Cables 3 4 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...
Page 104: ...Index Index 4 Stratus ftServer 2510 4410 and 6210 Systems Site Planning Guide R627...