This chapter contains an introduction for servicing the L180 Tape Library and
the basic components in it.
■
Service Clearances
shows the space requirements that you need to service the library.
Figure 1-1. Service Clearances
(C67109)
1. 2.6 m (8.5 ft)
2. 0.8 m (2.6 ft)
3. At all times, make sure at least 51 mm (2 in.) exists on the right and left sides of the library for airflow.
Note:
You might want to remove the left side cover when you replace the CAP motor and the theta
motor for easier access. Allow a minimum of 1 m (3.3 ft) to remove the cover.
2
3
C67109
1
Summary of Contents for L180
Page 1: ...L180 Tape Library Service Manual Document 95897...
Page 2: ......
Page 3: ...L180 Tape Library Service Manual...
Page 6: ...Summary of Changes iv Fifth Edition 95897 This page intentionally left blank...
Page 16: ...Tables xiv Fifth Edition 95897 This page intentionally left blank...
Page 44: ...Component Overview 1 12 Fifth Edition 95897 This page intentionally left blank...
Page 68: ...Configuration Overview 2 24 Fifth Edition 95897 This page intentionally left blank...
Page 254: ...Specifications A 28 Fifth Edition 95897 This page intentionally left blank...
Page 262: ...Index Index 8 Fifth Edition 95897 This page intentionally left blank...
Page 265: ......