background image

Operating instructions  

 

Main menu (operating mode) 

Parameter menu (information/programming mode) 

Changing parameter values 

28 

 

The boiler controller has two menus: the main menu (operating mode) when the lid is closed, and the parameter menu 

(information/programming mode) when the lid is open. Both menus and possibilities are explained in the next paragraphs. 

Main menu (operating mode) 



lid closed 

With the lid closed and by using the rotational switch (1) clockwise or anticlockwise 

the boilers’ operating mode (2) can be set. The available modes are: 

 

 

K

  Standby mode (only frost protection) 

F

  Automatic operation mode (heating and DHW) 

F

  Summer mode (only DHW, no heating) 

W1

  Service mode minimum load 

W2

  Service mode full load (limited by P9) 

 

Besides the operating mode, the display also shows the actual water flow tempera-

ture (3) and, in case of a lockout, a warning triangle (4) combined with a lockout 

code (5). The explanation of the lockout codes can be found in chapter 

“Lockouts”. 

Parameter menu (information/programming mode) 



lid open 

With the lid open and by using the rotational switch (1) clockwise or anticlockwise 

it’s possible to read/change certain values/parameters from the boiler controller. 

An arrow at the bottom of the display (2) indicates which parameter has been se-

lected. The available values/parameters are: 

 

P1    Actual / setpoint water flow temperature [ºC] 

P2    Actual / setpoint DHW temperature [ºC] 

P3    Actual temperature/capacity setpoint for boiler [ºC]* 

P4    -- 

P5    Actual outside temperature [ºC] (if sensor is connected) 

P6    Actual fluegas temperature [ºC] 

P7    -- 

P8    Actual low velocity header temperature [ºC] (if sensor is connected) 

P9    Actual / Limit boiler output [%] 

P10   Password for advanced settings 



Press the reset/programming button 

to select (the LED lights up) 



Turn the rotational switch until the 

desired DHW setpoint value has been 

reached 



Press the reset/programming button 

to confirm (the LED goes out) 



Close the lid. 

Output indications

 

 

Power to main gas valve

 

 

Power to ignition transformer

 

 

Fan control signal

 

 

Z

  Power to primary boiler pump

 

 

F

  Power to DHW pump/diverter valve 

Behind the lid you find an optical I/O 

connection (6), a reset/programming 

button (7) and an alarm/programming 

LED (8). Besides the parameter values/

settings, the display also shows additio-

nal information with regard to input and 

output indications to and from the boi-

ler:

 

 

Input indications

 

 

H

    Flame ionisation detected

 

 

SW    Water flow switch active

 

 

DW    Air pressure switch active

 

 

RT     Boiler enabled**

 

 

Bus    Bus communication active

 

 

Changing parameter values 

For changing any parameters, in the 

example parameter P2 (DHW setpoint), 

the following procedure should be car-

ried through: 



Open the lid (the arrow at the bottom 

of the display indicates parameter P1) 



Turn the rotational switch clockwise 

until the arrow indicates parameter P2 

The new value is now activated. All 

parameters can be changed by follo-

wing the same procedure as described 

above. 

**The boiler enable signal is equipped with a jumper in the standard delivery and therefore the boiler will normally be enabled. If a building 

management system is connected to provide the enable signal to the boiler (jumper should be removed), check the building management 

system if the boiler remains disabled. 

* P3 shows the actual temperature setpoint of the boiler, either coming from P1/P2 or from an additional (weather compensated) controller or 

building management system (2-10V). When the boiler capacity is controlled via a cascade manager or building management system (2-10V), 

P3 shows the actual capacity setpoint of the boiler. 

2     5       3      4            1 

2                        1 

6   7     8 

Summary of Contents for ECONOFLAME R3400

Page 1: ...sing Installation Operation Maintenance Manual STOKVIS ENERGY SYSTEMS 96R Walton Road East Molesey Surrey KT8 0DL Tel 020 8783 3050 0870 7707747 Fax 020 8783 3051 0870 7707767 E Mail info stokvisboile...

Page 2: ...startup 22 Combustion analysis 23 Air pressure switch 24 Check water flow 25 Check functionality of safety devices 26 Gas tightness check 26 Boiler shut down 26 Commissioning protocol 27 Operating ins...

Page 3: ...s to the following European standards 92 42 EEC Boiler efficiency directive 90 396 EEC Gas appliance directive 73 23 EEC Low voltage directive 89 336 EEC EMC directive EN 656 Gas fired central heating...

Page 4: ...adapts the modulation ratio automati cally to the heat demand requested by the system This is done by controlling the speed of the fan As a result the Whirlwind mixing system will adapt the gas ratio...

Page 5: ...max min C 135 60 Flue gas quantity max min m3 h 1423 356 1580 395 1848 462 2091 523 2334 584 CO2 level main burner natural gas H E L LL max min 10 0 9 3 CO2 level main burner liguid gas P max min 11...

Page 6: ...level main burner natural gas H E L LL max min 10 0 9 3 CO2 level main burner liguid gas P max min 11 0 11 0 CO2 level pilot burner natural gas H E L LL max min 10 0 10 2 CO2 level pilot burner ligui...

Page 7: ...88 88 88 H mm 1355 1355 1355 1355 1355 1355 H1 mm 1125 1125 1570 1420 1155 1377 B mm 1330 1330 1130 1130 1330 1330 B1 mm 1160 1210 1003 1053 1203 1253 B2 mm 665 665 565 565 665 665 B3 mm 170 120 127 7...

Page 8: ...8...

Page 9: ...max min m3 h 969 242 1076 307 1258 359 1424 407 1590 454 1756 502 CO2 level main burner natural gas H E L LL max min 10 0 9 3 10 0 9 3 CO2 level main burner liguid gas P max min 11 0 11 0 11 0 11 0 C...

Page 10: ...427 B mm 1330 1130 1130 1330 1330 B1 mm 1210 1003 1053 1203 1253 B2 mm 665 565 565 665 665 B3 mm 120 127 77 127 77 B4 mm 1146 946 946 1146 1146 B5 mm 65 115 65 115 65 D mm 300 350 350 400 400 W1 DN DN...

Page 11: ...re at 40 30 C max min C 59 36 Flue gas quantity max min m3 h 969 242 1076 307 1258 359 1424 407 1590 454 1756 502 CO2 level main burner natural gas H E L LL max min 10 0 9 3 10 0 9 3 CO2 level main bu...

Page 12: ...03 1053 1203 1253 B2 mm 615 665 565 565 665 665 B3 mm 120 120 127 77 127 77 B4 mm 1046 1146 946 946 1146 1146 B5 mm 100 65 115 65 115 65 D mm 300 300 350 350 400 400 D1 mm 250 250 300 300 355 355 W1 D...

Page 13: ...s Component Pcs Package R3400 R3600 Boiler fully assembled and tested 1 Mounted on wooden blocks with wooden border sealed in PE foil Adjustable feet 4 Cardboard box on top of boiler on R3407 R3410 al...

Page 14: ...140 1010 1310 500 210 1420 1010 500 215 1420 1110 500 220 1420 1210 500 225 1420 1310 500 1st Heat exchanger m kg L mm W mm H mm 120 1010 1150 160 120 1030 1150 150 135 1010 1310 160 180 1420 1010 160...

Page 15: ...00 1510 1425 150 325 2050 1250 150 330 2050 1350 150 335 2050 1450 150 2nd Heat exchanger m kg L mm B mm H mm 220 1510 1425 150 365 2050 1250 150 370 2050 1350 150 375 2050 1450 150 Frame m kg L mm B...

Page 16: ...n Removing the casing 16 Boiler transport Remove the casing before transporting the boiler in order to avoid damage to the casing parts during transportation Removing the casing is done as fol lows 1...

Page 17: ...is in the correct posi tion the wooden blocks 1 should be removed and the adjustable feet 2 with vibration absorption dampers should be adjusted to the right height Water and gas connections should b...

Page 18: ...lic connections The boiler should always be connected in such a way that water flow through the boiler can be ensured at all times Connect the flow 3 and return 1 con nection of the system tension fre...

Page 19: ...ength see planner documentation Construct horizonal ways with a mini mum angle of 3 Air intake connection 3 When using the boiler roomsealed The air intake can be connected if the boiler was ordered a...

Page 20: ...out by authorized personnel only Failure to respect this condition makes the guarantee void A protocol of the commissioning should be filled out see end of this chapter for example of commissioning pr...

Page 21: ...or which gas type the boiler should be commissioned Condensate connection Remove the syphon 2 from the con densate connection Fill it with water and place it back in the original posi tion Make sure t...

Page 22: ...ation is correct Remove any air from the pump by removing the end cap of the pump motor housing It s recommended to keep the boiler at 50 load for a while after the first startup as this is the easies...

Page 23: ...or full load The combustion settings for the pilot burner can be adjusted using the adjustment screw on the pilot gas valve 6 The combustion settings for the main burner can be adjusted using the adju...

Page 24: ...be 0 8 mbar Turn the dial on the switch 2 counter clockwise until the end Reduce the setting on parameter P17 step by step until the pressure differential is 0 4 mbar Slowly turn the dial on the swit...

Page 25: ...nal data p measurement Check the pressure difference over the boiler p flow return when the boiler pump is running burner on is not requi red The nominal p for each boiler type can be found in the tab...

Page 26: ...n a standard boiler are a water flow tem perature sensor water flow switch minimum gas pressure switch and ioni sation electrode These devices can be checked as described below Ionisation electrode 6...

Page 27: ...switch checked Min gas pressure switch setting mbar Ignition time burner sec Combustion analysis 100 load 50 load Min load Gas consumption m3 h m3 h m3 h Gas pressure mbar mbar mbar CO2 pilot burner O...

Page 28: ...ess the reset programming button to select the LED lights up Turn the rotational switch until the desired DHW setpoint value has been reached Press the reset programming button to confirm the LED goes...

Page 29: ...ition and ionisation electrodes Clean the condensate receptacle Clean and refill the syphon Check the water pressure of the sys tem Check the water quality of the system water as well as supply water...

Page 30: ...led information Combustion analysis Check the combustion at full load and minumum load correct the settings if necessary An additional reference check at 50 load is recommended Consult the chapter com...

Page 31: ...gnition time burner sec Combustion analysis 100 load 50 load Min load Gas consumption m3 h m3 h m3 h Gas pressure mbar mbar mbar CO2 Pilot burner O2 Pilot burner CO Pilot burner ppm ppm ppm NOx Pilot...

Page 32: ...pply check ignition spark increase gas valve setting min load alan key screw 5 Lockout Flame ionisation signal lost during operation Check gas supply pressure during operation check gas valve setting...

Page 33: ...parameters P11 P40 Check parameter settings of P11 P40 change value of one parameter within P11 P40 lockout disappears change all parameters back to original settings 31 Lockout CRC error in boiler s...

Page 34: ...kits The diagrams contain average values as all sensors are liable to tolerances When measuring the resistance values the boiler should always be switched off Measure close to the sensor in order to...

Page 35: ...owing standards EN 656 EN 15417 EN 13836 EN 55014 1 2 EN 61000 3 2 3 EN 60 335 1 2 and in accordance with the guidelines of directives 92 42 EEC boiler efficiency directive 90 396 EEC gas appliance di...

Page 36: ......

Page 37: ......

Page 38: ...S ENERGY SYSTEMS 96R Walton Road East Molesey Surrey KT8 0DL Tel 020 8783 3050 0870 7707747 Fax 020 8783 3051 0870 7707767 E Mail info stokvisboilers com Website www stokvisboilers com 420010567700 12...

Reviews: