stilum pila2 Mounting Instructions Download Page 2

©  stilum GmbH, Gewerbegebiet Larsheck, 56271 Kleinmaischeid  •  Tel. +49 (0) 2689 92790-0  •  All rights and product modifications reserved.

State: 11/2012 · S. 2

Mounting instructions for shooting target „pila2“ 

Item No. 552011401

Diagram 2: Side view with dimension details „pila2“

Play level

1.  Select the play equipment location in consideration of the required safety 

area (see Diagram 3: Ø 5500 mm). 

2.  Carry out excavation work for the foundation anchor as shown in Diagram 

2. After excavation, compress the foundation floor. 

Note

: Make sure that the 

play equipment is marked with “Play level”! Pay attention to items marked 
„game level“ of play equipment! 

3.  Set up the concrete foundation acc. to the dimensions indicated (LxWxH 

1000 x 1000 x 400 mm) with horizontal reinforcement (BST 500 S) in the 
quality class B 25. Make sure that the foundation anchor included in the deli-
very is cast into the foundation in such a way that the upper angle frame lies 
horizontally and fl ush mount with the surface of the foundation.

4.  During a setting period of 10 – 14 days, depending on weather conditions 

and foundation size, recording on the device to lock.

5.  After the setting period clean the surface of the foundation, place the pre-

mounted play equipment onto it and screw the base plate of the play equip-
ment onto the foundation anchor.

6.  Seal the foundation with the safety cover required for the height of fall indica-

ted. Set up impact-absorbing playground surfacing according to EN 1177 HIC 
1000.  
Recommended surface material: grass, sand, bark mulch, gravel, synth. fall 
protection. (Critical drop height ≤ 1000 mm)

7.  Do not allow children to use the equipment before the installation has been 

finished.   

Reinforcement plan: 

Concrete foundation with rein-

forcement
Main foundation: BSt 500S 
Ever 4 stirrups Ø 8 mm lengthwise and cross 
Concrete cover h´= 3 cm
Concrete quality class B25