Safety Concerns 

  

  

  

  

 

Quickstart Installation Checklist 

(Refer to main manual for complete installation instructions). 
 

1.  Connect 3-phase power based on nameplate data. 
2.  Apply power to chiller for at least 24 hours prior to start up. 
3.  Install properly sized plumbing between portable chiller and primary 

processing equipment (supply and return).  

4.  Ensure proper pump rotation. (The pump motor should be turning 

clockwise while looking at the motor fan end). 

 

 

Unit Operation 

(Refer to main manual and controller manual for complete operating 
instructions). 

Start Up 

1.  Add fluid to the reservoir tank until the level is near the top of the tank. 
2.  Turn power switch to ON position.  

3.  Depress the "On|Off" 

 

button to start the pump.  

4.  Maintain the minimum tank level based on size of tank.  Handheld display will notify you about tank level. 

5.  To change the setpoint, press the menu 

 

button, press the up 

 or down 

 

arrow button to highlight SETTINGS 

and press enter. Press the enter 

 

button to move the cursor to the CHILLED FLUID SP line.  Press the up 

 or 

down 

 button to increment or decrement the value.  Press enter 

 to accept the value.  Press the escape 

 

button twice to return to the main status screen. 

Shut Down 

1.  Depress the “On|Off” 

 

button to shut down chiller. 

2.  Maintain power switch in the ON position.

 

 

 

Standard Display 

 