ACCUMULATOR TESTING 

PROCEDURE

To  check  or  charge  the  accumulator  the  following 

equipment is required:
31254  Charge  Kit:  which  includes  the  following  (see 

Figure 2).

• 

Accumulator Tester (Part Number 02835).

• 

Charging Assembly  (P/N  15304)  Includes  a  liquid 

filled gauge w/snub valve, hose and charge fitting.

• 

NITROGEN  bottle  with  a  800  psi/56  bar  minimum 

charge (NOT included in 31254 Charge Kit.)

1. 

Remove the valve cap assembly from the sinker drill 

(see Figure 2 for location).

2. 

Remove the protective cap and loosen the 5/8-inch 

hex  locking  nut  on  the  tool  charging  valve  1-1/2 

turns.

3.  Holding the chuck end of Accumulator Tester (P/N 

02835)  turn  the  gauge  fully  counterclockwise  to 

ensure that the stem inside the chuck is completely 

retracted.

4.  Thread the tester onto the accumulator charging 

valve.  Do  not  advance  the  gauge-end  into  the 

chuck-end. Turn  as  a  unit.  Seat  the  chuck  on  the 

accumulator charging valve and hand tighten only.

5. 

Advance the valve stem of the tester by turning the 

gauge-end clockwise until a pressure is read on the 

gauge (charge pressure should be 600–700 psi/42–

48 bar).

6.  If pressure is OK, unscrew the gauge-end from the 

chuck to retract the stem, then unscrew the entire 

tester assembly from the accumulator charging 

valve. If pressure is low, charge the accumulator as 

described in the following paragraph.

7. 

Tighten  the  5/8-inch  hex  locking  nut  on  the  tool 

charging valve. Be careful not to overtighten. Install 

the protective cap and valve cap assembly.

ACCUMULATOR CHARGING

1. 

Perform  Steps  1  through  4  of  the  accumulator 

testing procedure above.

2. 

Connect  the  chuck  of  the  charging  assembly  to 

the charging valve on the accumulator tester or, if 

preferred, remove the tester from the charging valve 

and connect the charging assembly chuck directly to 

the charging valve.

3.  Adjust the regulator to the charging pressure of 600 

psi/42 bar.

Note: It may be necessary to set the gauge at 650-

700  psi/45-48  bar  to  overcome  any  pressure  drop 

through the charging system.

4.  Open the valve on the charging assembly hose.

5. 

When the accumulator is fully charged close the 

valve on the charging assembly hose and remove 

the charging assembly chuck from the accumulator 

tester or tool charging valve.

6. 

If the accumulator tester has been used, be sure to 

turn  the  gauge-end  fully  counterclockwise  before 

removing the tester from the charging valve of the 

tool.

7. 

Tighten  the  5/8-inch  hex  locking  nut  on  the  tool 

charging valve and replace the protective cap.

8. 

Replace the valve cap assembly.

CHARGING THE ACCUMULATOR

Summary of Contents for SK47

Page 1: ...2014 STANLEY Black Decker Inc New Britain CT 06053 U S A 10323 2 2018 Ver 9 USER MANUAL Safety Operation and Maintenance SK47 HYDRAULIC SINKER DRILL...

Page 2: ......

Page 3: ...y Note The warranty validation record must be submitted to validate the warranty SERIOUS INJURY OR DEATH COULD RESULT FROM THE IMPROPER REPAIR OR SERVICE OF THIS TOOL REPAIRS AND OR SERVICE TO THIS TO...

Page 4: ...messages that follow this symbol to avoid possible injury or death This safety alert and signal word indicates an imminently hazardous situation which if not avoided will result in death or serious in...

Page 5: ...connecting Use only lint free cloths Failure to do so may result in damage to the quick couplers and cause overheating of the hydraulic system Do not operate the tool at oil temperatures above 140 F 6...

Page 6: ...ESSURING SYSTEM SYSTEM PRESSURE HOSE MUST ALWAYS BE CON NECTED TO TOOL IN PORT SYSTEM RETURN HOSE MUST ALWAYS BE CONNECTED TO TOOL OUT PORT REVERSING CONNECTIONS MAY CAUSE REVERSE TOOL OPERATION WHICH...

Page 7: ...TH TO REMOVE DIRT AND MOISTURE AND TEST HOSE FOR MAXIMUMALLOWABLE CURRENT LEAKAGE INACCORDANCE WITH SAFETY DEPARTMENT INSTRUCTIONS SEE OTHER SIDE SIDE 2 D O N O T R E M O V E T H I S T A G 3 DO NOT EX...

Page 8: ...Pressure 2500 175 1 25 4 Return 2500 175 13 16 49 60 up to 25 up to 8 5 8 16 Pressure 2500 175 3 4 19 Return 2500 175 13 16 49 60 26 100 8 30 3 4 19 Pressure 2500 175 1 25 4 Return 2500 175 Figure 1 T...

Page 9: ...operator discomfort at the tool Filter minimum full flow filtration 25 microns 25 microns 25 microns 25 microns Sized for flow of at least For cold temp startup and maximum dirt holding capacity 30 G...

Page 10: ...si Supplying less than these specifications may result in inadequate extraction of rock cuttings cause cuttings to migrate up the drill steel and into the tool and result in tool damage diminish drill...

Page 11: ...e bit is lifted from the hole 15 When the tool drill steel and bit have been removed from the drill hole turn the valve lever OFF and turn the hydraulic supply circuit control valve OFF before changin...

Page 12: ...LEY Supply hoses must have a minimum working pressure rating of 2500 psi 172 bar Do not exceed the rated flow and pressure See Specifications in this manual for correct flow rate and pressure rating R...

Page 13: ...ract the stem then unscrew the entire tester assembly from the accumulator charging valve If pressure is low charge the accumulator as described in the following paragraph 7 Tighten the 5 8 inch hex l...

Page 14: ...14 SK47 User Manual Figure 2 Charging the Accumulator CHARGING THE ACCUMULATOR...

Page 15: ...blocked Remove restriction Orifice plug blocked Remove restriction Fluid too hot above 140 F 60 C or too cold below 60 F 16 C Check power unit for proper fluid temperature Bypass cooler to warm the fl...

Page 16: ...ith Air 7 8 in 22 mm Hex 4 1 4 in 108 mm H Thread 24 in 61 cm UC 05174 Carbide Rock Bits for use with Air 1 3 8 in 34 9 mm Diameter H Thread 05177 1 1 2 in 38 1 mm Diameter H Thread 05178 2 in 50 8 mm...

Page 17: ...SK47 User Manual 17 SK47 PARTS ILLUSTRATION 83 Motor Assy...

Page 18: ...VALVE 32 08097 1 VALVE SPOOL 33 08098 1 SPRING 34 08104 1 O RING PLUG 35 04934 1 CUP SEAL 36 04780 1 WASHER 37 04386 1 CUP SEAL 38 02022 1 O RING 39 00473 1 O RING ITEM PART NO QTY DESCRIPTION 40 0493...

Page 19: ......

Page 20: ...STANLEY Infrastructure 6430 SE Lake Road Portland Oregon 97222 USA 503 659 5660 Fax 503 652 1780 www stanleyinfrastructure com...

Reviews: