Spirax Sarco UIB30 Installation And Maintenance Instructions Manual Download Page 3

IM-P113-02 

CMGT Issue 6

3

UIB30 and UIB30H Sealed Inverted Bucket Steam Traps for use with Pipeline Connectors

Safe operation of these products can only be guaranteed if they are properly installed, commissioned, 

used and maintained by qualified personnel (see Section 1.11 ) in compliance with the operating 

instructions. General installation and safety instructions for pipeline and plant construction, as 

well as the proper use of tools and safety equipment must also be complied with.

Warning

The inner and outer gaskets used when installing/maintaining the UIB to a PC_ pipeline connector 

contain thin stainless steel support rings which may cause physical injury if not handled and 

disposed of carefully.

 

1.1 Intended use

Referring to the Installation and Maintenance Instructions, product marking and Technical 

Information Sheet, check that the product is suitable for the intended use/application. The UIB30 

and UIB30H comply with the requirements of the Pressure Equipment Directive (PED) and fall 

within category 'SEP'. 

It should be noted that products within this category are required by the Directive not to carry 
the 

 mark.

i) The product has been specifically designed for use on steam, compressed air and water/ 

condensate which are in Group 2 of the above mentioned Pressure Equipment Directive.

ii) Check material suitability, pressure and temperature and their maximum and minimum values. 

If the maximum operating limits of the product are lower than those of the system in which it 

is being fitted, or if malfunction of the product could result in a dangerous overpressure or 

overtemperature occurrence, ensure a safety device is included in the system to prevent such 

over-limit situations.

iii) Determine the correct installation situation and direction of fluid flow. 
iv) Spirax Sarco products are not intended to withstand external stresses that may be induced 

by any system to which they are fitted. It is the responsibility of the installer to consider these 

stresses and take adequate precautions to minimise them.

v)  Remove protection covers from all connections and protective film from all name-plates, where 

appropriate, before installation on steam or other high temperature applications.

1.2 Access

Ensure safe access and if necessary a safe working platform (suitably guarded) before attempting 

to work on the product. Arrange suitable lifting gear if required.

1.3 Lighting

Ensure adequate lighting, particularly where detailed or intricate work is required.

1.4 Hazardous liquids or gases in the pipeline

Consider what is in the pipeline or what may have been in the pipeline at some previous time. 

Consider: flammable materials, substances hazardous to health, extremes  of  temperature.

1. Safety information

Summary of Contents for UIB30

Page 1: ...UIB30H 1 Safety information 2 General product information 3 Installation 4 Commissioning 5 Operation 6 Maintenance 7 Spare parts 1130050 6 UIB30 and UIB30H Sealed Inverted Bucket Steam Traps for use...

Page 2: ...IM P113 02 CMGT Issue 6 2 UIB30 and UIB30H Sealed Inverted Bucket Steam Traps for use with Pipeline Connectors...

Page 3: ...ove mentioned Pressure Equipment Directive ii Check material suitability pressure and temperature and their maximum and minimum values If the maximum operating limits of the product are lower than tho...

Page 4: ...umables Before starting work ensure that you have suitable tools and or consumables available Use only genuine Spirax Sarco replacement parts 1 10 Protective clothing Consider whether you and or other...

Page 5: ...amage in environments where they may be exposed to temperatures below freezing point 1 15 Disposal Unless otherwise stated in the Installation and Maintenance Instructions this product is recyclable a...

Page 6: ...y complies with the requirements of the Pressure Equipment Directive PED Certification This product is available with certification to EN 10204 3 1 Note All certification inspection requirements must...

Page 7: ...C 720 psi g 100 F TMA Maximum allowable temperature 425 C 28 bar g 800 F 405 psi g Minimum ambient temperature 30 C 22 F PMO Maximum operating pressure for saturated steam service 32 bar g 464 psi TMO...

Page 8: ...e screws finger tight until the mating gasket faces are in parallel intimate contact Tighten the screws evenly and gradually to the recommended torque value see Table 1 Open isolation valves slowly un...

Page 9: ...ional extras The cover 1 is also available with a threaded drain plug and connection 13 14 in 3 8 NPT NPT or BSP to allow for drainage If this option is required it must be specified at the time of or...

Page 10: ...dy is parallel to the connector Tighten the screws evenly and gradually to the recommended torque see Table 1 Open isolation valves slowly until normal operating conditions are achieved Check for leak...

Page 11: ...et 10 11 12 How to order spares Always order spare parts by using the description given in the column headed Available spares and state the size model no and pressure rating of the trap Examples 1 Con...

Page 12: ...IM P113 02 CMGT Issue 6 12 UIB30 and UIB30H Sealed Inverted Bucket Steam Traps for use with Pipeline Connectors...