SpectraLink Corporation
Installation—NetLink Telephony Gateway
NetLink SVP Server
Part Number: 72-0065-01-G.doc
Page 9
2. Installation
Overview
Installation has several phases. In some cases, a separate person is responsible for each
phase. It is important to coordinate the activities among the persons involved.
The customer or vendor installs the access points per the
Configuration Note
for the
access point being used. This is normally done before the NetLink Telephony Gateway
installation, but should be done before step 3 below.
This document covers the first two steps that are usually done by the customer up to the
point of installing and connecting the NetLink Telephony Gateway(s) to the telephone
demarc blocks and LAN access device. At that point, a qualified SpectraLink installer
assists the customer in completing the remaining steps.
1.
Site Preparation
–
done by the customer or a wire technician/contractor.
2.
NetLink Telephony Gateway Installation
– done by the customer or
SpectraLink.
If five or more NetLink Telephony Gateways are to be installed, a NetLink SVP
Server is required and would also be installed in this step.
3.
NetLink Telephony Gateway Configuration
– done by the customer or
SpectraLink per
NetLink Telephony Gateway: Setup and Maintenance
.
If a NetLink SVP Server has been installed, its configuration would also be done
in this step.
4.
NetLink Wireless Telephone Configuration
– done by the customer or
SpectraLink per
NetLink Wireless Telephone: Setup and Administration
.
5.
System Certification
– done after installation to confirm the system is working
properly per
NetLink Wireless Telephone: Setup and Administration
.
For more information about NetLink system architecture and components, please see
NetLink Telephony Gateway: Setup and Maintenance.