12/05
ID# M881111
13
4
3
Fill hole completely with concrete.
6.
1" (2.54 cm)
1" (2.54 cm)
1" (2.54 cm)
5
GSLV09.EPS
211121
1" (2.54 cm)
7.
Tamp down concrete to release air pockets and build drainage hill. Level pole section in all
directions several times while concrete is curing.
1" (2.54 cm)
1" (2.54 cm)
1" (2.54 cm)
SIDE VIEW
Make a reference
mark here for anti-
skid tape.
NOTE:
DRAINAGE
HILL
IMPORTANT!
CONTINUE ON TO NEXT STEP. DO NOT WAIT FOR CONCRETE TO CURE.
Keep flange pushed
down to concrete
and leveled.
NOTE:
IMPORTANT!
WAIT A MINIMUM OF 24 HOURS BEFORE GOING ON TO NEXT STEP.
CONCRETE MUST CURE.
PLAYING SURFACE