3-E
HDR-CX300/CX300E/CX305E/CX350/CX350E/CX350V/CX350VE/CX370/CX370E/CX370V/XR350/XR350E/XR350V/XR350VE_L2
3. ASSEMBLY
Assembly-1:
The Method of attachment of FP-1178
Flexible Board
1
Fold dotted line parts of the FP-1178 flexible
board as shown in figure.
FP-1178 Flexible Board
Valley
fold
Valley fold
Mountain fold
Mountain fold
Adhesive tape
Adhesive tape
Adhesive tape
2
Put on the FP-1178 flexible board to the hinge assy
as shown in figure.
3
Install the Flexible Clamp.
4
Install the Hinge Cover (U) with magnet and
the Hinge Cover (C).
5
Roll the FP-1178 flexible board 1.5 times
in the hinge assy as shown in figure.
1.5 times
Hinge Cover (C)
Hinge Cover (U),
Magnet
Hinge Assy
Adhesive Part
Claws
Flexible clamp
XR350/XR350E/XR350V/XR350VE
CX300/CX300E/CX305E/CX350/CX350E/CX350V/
CX350VE/CX370/CX370E/CX370V
Assembly-2:
Route the DC jack harness as
shown below.
DC Harness
DC Harness
ST-227 Board
ST-227 Board
FP-1181
Flexible Board
DC Harness
Assembly-3:
Radiation Sheet (B) Putting Position
Radiation Sheet (B)
Assembly-4:
1010 Radiation Sheet Putting Position
Valley Fold
1010 Radiation Sheet
FP-1180
Flexible Board
Assembly-5:
936 Radiation Sheet,
Radiation Sheet (F) Putting Position
Don’t Pile up the two sheets
VC-588 Board
Radiation Sheet (F)
936 Radiation Sheet
VC-588 Board
Assembly-6:
How to Fold the FP-1181 Flexible Board
FP-1181 Flexible Board
Assembly-7:
The Method of Attachment of
the FP-1180 Flexible Board
FP-1180
Flexible Board
MS-430 Board