If the discharge has stopped due to the minimum state of charge, the storage system re-
mains in this state until the PV system starts to produce electrical power again. From then
on, the batteries of the storage system are charged and as soon as the state of charge ex-
ceeds the minimum limit, the surplus power is used to supply the electrical consumers in
the backup circuit.

4.1.3 Backup operation - overload behaviour

Case 1: Overload detection by fuse

The integrated fuse (miniature circuit breaker F3.P) of the sonnenProtect protects the en-
tire system against overload.

When the fuse trips, the storage system will still be in backup operation (Eclipse will turn

green

), but the electrical consumers in the backup circuit will no longer be supplied with

power!

„

In this case, switch off the electrical loads or reduce their power consumption and then
switch on the miniature circuit breaker F3.P in the sonnenProtect.

Case 2: Overload detection by storage system

In special overload cases, the control of the storage system reacts earlier than the integ-
rated fuse of the sonnenProtect. In this case, the miniature circuit breaker inside the
sonnenProtect does not trip, the backup power is instead stopped by the control of the
storage system. The eclipse of the storage system signals this by turning 

orange

.

When this happens, there are two options:

1.

The overload is removed: The storage system restarts the backup operation after a few
minutes and the eclipse changes from 

orange

 to 

green

.

2. The overload remains: The storage system tries to resume backup operation twice. If it

is switched off a third time, the backup operation remains disabled until the grid outage
is over. The eclipse will continue to glow 

orange

.

Summary of Contents for sonnenProtect 2500

Page 1: ...Operating instructions for operators sonnenProtect 2500 for sonnenBatterie hybrid 9 53 KD 536 Part no 1000051 Version 02 info sonnen de sonnen de ...

Page 2: ...sonnen com au Document Document number 536 Part number 1000051 Version 02 Valid for AU NZ Publication date 05 02 2021 9007199366748683 IMPORTANT Read this documentation carefully before installation operation Retain this document for reference purposes EN Operating instructions sonnenProtect 2500 ...

Page 3: ...ge inside the sonnenProtect 6 3 Product description 7 3 1 Technical data 7 3 2 System components of the sonnenProtect 8 3 3 Type plate 8 3 4 Symbols on the outside of the sonnenProtect 9 4 Operation 10 4 1 Function 10 4 1 1 Grid operation no grid outage 10 4 1 2 Backup operation grid outage 11 4 1 3 Backup operation overload behaviour 12 4 2 Setting the backup buffer 13 5 Switching off the sonnenP...

Page 4: ...s document Complete designation Designation in this document sonnenProtect 2500 sonnenProtect sonnenBatterie hybrid 9 53 Storage system 1 3 Explanation of symbols DANGER Extremely dangerous situation leading to certain death or serious injury if the safety information is not observed WARNING Dangerous situation leading to potential death or serious injury if the safety information is not observed ...

Page 5: ...roduct doc umentation of the appropriate storage system The sonnenProtect must only be installed and used at suitable installation location The transport and storage conditions must be observed Especially the following uses are not permissible Operation in flammable environments or areas at risk of explosion Operation in locations at risk of flooding Operation outdoors Failure to comply with the c...

Page 6: ...s and only when in perfect working order Safety devices must never be overridden blocked or tampered with The interfaces of the sonnenProtect and the storage system must be connected in ac cordance with the product documentation All repairs on the sonnenProtect must be performed by authorised service technicians only 2 5 Voltage inside the sonnenProtect 5 min The sonnenProtect contains live electr...

Page 7: ...itch to emergency operation takes place automatically through the storage system Switchover time max 15 seconds Threshold power none starting from 0 W Dimension Weight Dimension H W D in mm 230 200 122 Weight in kg 4 3 Safety Protective devices Protection class I PE conductor Degree of Protection IP30 Overvoltage category III Protective functions Overcurrent protection fault current protection Res...

Page 8: ...butor 6 Miniature circuit breaker F3 P 3 3 Type plate The type plate is located on the outer surface of the sonnenProtect The type plate can be used to uniquely identify the sonnenProtect The information on the type plate is required for the safe use of the system and for service matters The following information is specified on the type plate Item designation Item number Technical data A duplicat...

Page 9: ...ical voltage Wait five minutes after switching off ca pacitor de energising time CE mark The product meets the requirements of the applicable EU Directives WEEE mark The product must not be disposed of in household waste dispose of it through environmentally friendly collection centres Observe the documentation The documentation contains safety in formation ...

Page 10: ...ted to phase L1 6 Storage system 2 Consumer connected to phase L2 7 Battery of the storage system 3 Consumer connected to phase L3 8 PV system 4 Consumer connected to backup circuit 9 Public electricity grid 5 sonnenProtect In grid operation the consumers connected to phase L1 to L3 and the consumers connec ted to the backup circuit 1 4 are connected to the public electricity grid 9 All con sumers...

Page 11: ... house 4 are thereby supplied with electrical power Consumers connected to the phase L1 L2 or or L3 1 3 will not be supplied with electrical power The switchover from grid to backup operation is signaled by the sonnen Eclipse light ring on the storage system The color of the sonnen Eclipse changes from white normal opera tion to green backup operation Electrical power generated by the PV system 8 ...

Page 12: ...l no longer be supplied with power In this case switch off the electrical loads or reduce their power consumption and then switch on the miniature circuit breaker F3 P in the sonnenProtect Case 2 Overload detection by storage system In special overload cases the control of the storage system reacts earlier than the integ rated fuse of the sonnenProtect In this case the miniature circuit breaker in...

Page 13: ...The sonnenProtect was set up by the installer using the commissioning assistant 2 Proceed as follows to access the storage system web interface Enter the following address into your browser s address line https find my sonnen batterie com The following window appears 12345 123 456 78 99 Click on the blue LAN IP number The login page appears Log in as user with the following password sonnenUser3552...

Page 14: ...4 Operation 14 20 Operating instructions sonnenProtect 2500 ...

Page 15: ...in the relevant product documentation After switching off the consumers connected to the backup circuit s can no longer be supplied with electrical energy from the battery of the storage system NOTICE Deep discharge of the battery modules Destruction of the battery modules Do not disconnect the storage system from the public electricity grid for long periods of time Never continue to operate batte...

Page 16: ...aken Every 6 months Check the function of the RCD with help of the Test key Table 3 Checking function 6 2 Cleaning NOTICE Use of unsuitable cleaning agent and or excessive water Material damage because of scratched surfaces and or damage caused by penetration of water Do not use scouring cloths sponges or cleaning agent Use only moist cloths not wet cloths to clean the system Do not use water jets...

Page 17: ...tion of the sonnenProtect Danger to life due to electrocution The sonnenProtect must only be uninstalled by authorised electricians 7 2 Disposal Illustration 4 WEEE symbol The sonnenProtect must not be disposed of as do mestic waste Dispose of the sonnenProtect in an environ mentally friendly way through suitable collec tion systems ...

Page 18: ... charge state and therefore damage the batteries If the PV system generates electrical power the backup operation will continue as soon as excess power is available If the PV system does not generate elec trical power the only thing to do is wait until the grid outage passes and the public electrical grid once again starts supplying electrical energy Then the sonnenProtect automatically switches t...

Page 19: ...er consumption does not exceed the nominal power or when switching on the maximum power of the sonnenProtect Then switch on the miniature circuit breaker F3 P again The storage system automatically restarts the backup opera tion Backup operation stops The RCD F4 P in the sonnenProtect has switched off The eclipse of the storage system is green The RCD has detected fault currents in the backup circ...

Page 20: ...sonnen GmbH Am Riedbach 1 D 87499 Wildpoldsried ...

Reviews: