Quick Installation Guide

—— 

BMS Parallel Box-II

Packing List (BMS Parallel Box-II)

I

III

II

Battery Installation

IV

Overview of Installation

V

Installation Prerequisites

Terminals of the BMS Parallel Box-II

Note: The Quick Installation Guide briefly describes required installation steps. If you have any questions, refer to the  

Installation

 

Manual for more detailed information. 

NOTE!

Ensure that the installation location meets the following conditions:

The building is designed to withstand earthquakes
The location is far from the sea to avoid salt water and humidity,

over 0.62 miles

The floor is flat and level
There are no flammable or explosive materials, at a minimum of 3ft
The ambience is shady and cool, away from heat and direct sunlight
The temperature and humidity remains at a constant level
There is minimal dust and dirt in area
There are no corrosive gases present, including ammonia and acid vapor 
Where charging and discharging, the ambient temperature ranges from 32°F to 113°F

   

The Solax battery module is rated at IP55 and thus can be installed outdoors as well as indoors. However, if 

installed outdoors, do not allow the battery pack to be exposed to direct sunlight and moisture.

ŸŸŸŸŸŸŸŸŸŸ
Ÿ
Ÿ
Ÿ
Ÿ
Ÿ
Ÿ
Ÿ
Ÿ

In practice, the requirements of battery installation may be different due to enviroment and locations.  

In that case, follow up the exact requirements of the local laws and standards.

NOTE!

If the ambient temperature exceeds the operating range, the battery pack will stop operating to protect itself. 

The optimal temperature range for operation is 15°  to 30°

Frequent exposure to harsh temperatures may 

C

C. 

deteriorate the performance and lifetime of the battery module.

NOTE!

- Match the box with the bracket.
M4 screws. (torque:(1.5-2)Nm) 

- Drill two holes with  driller
- Depth: at least 3.15in

- Lock the joint between hanging board and wall bracket
 with M5 screws. (torque:(2.5-3.5)Nm)

The bracket needs to be removed from the box. 

Group 1

Group 2

+
-

+

-

+
-

Battery module

Battery module

Battery module

Battery module

Battery module

Battery module

Battery module

Battery module

Quick Installation Guide

 x1

Power 

 

Cable (-)

 x1(2m)

Power 

 

Cable (+)

 x1(2m)

Ring Terminal x1

Grounding Nutx1

Installation Manual x1

Rotation Wrench

x1

Expansion screw

x2

Expansion tube

x2

Copyright Declaration

The copyr ight of this manual belongs to SolaX Power 
Co.,Ltd.. Any cor poration or individual should not 
plagiar ize, par titially copy or fully copy(including 

Triple Powe r Parallel Box

User Manual

Quick Installation Guide

—— 

BMS Parallel Box-II

Power 

 

Cable (-)

 x2(1m)

Power 

 

Cable (+)

 x2(1m)

RS485 

 

Cable

 x2(1m)

CAN 

 

Cable 

 x1(2m)

Power cable disassembling toolx1

XII

XIII

XIV

Object

Mark

Description

B1+

RS485

-

2

B2+

BAT-
CAN

/

Battery module communication of group 1

Battery module communication of group 2

Connector B2+ of Box to + of battery module of group 2

Connector CAN of Box to CAN of inverter
Air Valve
GND

RS485

-

1

XI

X

ON/OFF
POWER

Circuit Breaker
Power Button

DIP

DIP Switch

XII

XIII

XIV

BAT+

Connector BAT+ of Box to BAT+ of inverter
Connector BAT- of Box to BAT- of inverter

B2-

Connector B2- of Box to - of battery module of group 2

B1-

GND

Connector B1+ of Box to + of battery module of group 1

Connector B1- of Box to - of battery module of group 1

I

II

VI 

IV

VII  IX 

X

XI

III

IV V

VIII

NOTE!

When installing the battery for the first time, the manufacturing date between battery modules 

should not exceed 3 months

.

-If the battery is not used for more than 9 months, the battery must be charged to at least 

SOC 50 % each time.

-If the battery is  replaced 

the SOC between the batteries used should be as consistent as 

possibe, with a maxium difference of ±5 %.

-If you want to expand your battery system capacity, please make sure your existing system 

capacity's SOC is about 40%. The expansion battery is required to be manufactured within 6 

months; If more than 6 months, recharge the battery module to about 40%.