background image

A3

Assembly

General safety instructions

Ensure that any work on the PV system (installation, commissioning, maintenance, repair, etc.) is performed
by qualified professionals.

Observe all local and national code requirements for the prevention of accidents, including those that may
supersede this installation guide.

Ensure that fall protection is used on buildings that are greater than 3 m tall.

Protect persons on the ground against falling objects with appropriate barriers.

Observe any safety instructions provided with other system components.

Comply with any local codes and standards applicable in the relevant country for installation and commis-
sioning.

The system connection to the public grid may only be performed by a qualified electrician who may be
required to provide a certificate from the respective utility (Regulations in the relevant country must be
observed.)

For installation in roof areas, observe the applicable rules and standards for the respective country.

Special safety instructions

Observe installation instructions for modules and grid connected inverters as well as the installation and
wiring diagram enclosed with the delivered system.

The work should be performed by a qualified professional.

Ensure that all bolted connections are tightened to a torque of 20 Nm.

Summary of Contents for Suntub

Page 1: ...SolarWorld And EveryDay is a SunDay www solarworld de July 2009 Flat roof assembly system Design and installation...

Page 2: ...nts are used in order to ensure trouble free operation of your PV system The directions contained here are intended to assist you in properly installing your Suntub Assembly System Since individual ci...

Page 3: ...ion Page 8 B 1 Dimensions Page 8 B 2 Required ballast load Page 10 B 3 Shading table Page 12 C 1 Setup Page 15 C 2 Module connection Page 16 C 3 Grounding Page 17 Maintenance Cleaning Liability A Safe...

Page 4: ...he form of the fully insulated plug contacts the following points must be observed when handling solar modules to avoid the risk of fire sparking and fatal electric shock Do not install solar modules...

Page 5: ...hat the runoff of rainwater is not impeded Consider any physical or structural issues Any assessment of structural or functional suitability of the roof to support the PV array should be conducted by...

Page 6: ...omply with any local codes and standards applicable in the relevant country for installation and commis sioning The system connection to the public grid may only be performed by a qualified electricia...

Page 7: ...ween 0 and All mandatory framework conditions and technical data are summarized in the following table Components 1 Module 2 Clamp 3 Aluminium profile to be inserted Suntub right part 5 Suntub left pa...

Page 8: ...ght and the system location The required ballast loads have been calculated based on extensive wind tunnel tests and can be taken from the tables The following tables are applicable only with an avail...

Page 9: ...edge area edge area of the system first and last row plus the last two units of a row The loads can be reduced for interior areas Centre ballast column 3 The edge area of the roof should be kept clea...

Page 10: ...20 2 2 38 2523 3 3851 35 9 3302 3095 2920 2 2 38 4 228 3851 35 9 3302 3095 2920 2 5 12 228 3851 35 9 3302 3095 2920 6 5355 12 228 3851 35 9 3302 3095 B3 Shading table Sample calculation of required ba...

Page 11: ...e Suntub with the flat surface facing south so that the modules are tilted to face the incoming sunlight The side distance between the modules when fully assembled should be at least 8 mm for the setu...

Page 12: ...ed loads according to the system plan Gravel or concrete blocks may be used for example The ballast must be distributed evenly 3 Aluminium profile installation Next the two aluminium profiles are inse...

Page 13: ...e Next the top clamping connections can be installed After the module has been aligned all bolts can be tightened tightening torque 20Nm The modules must be centered on the Suntub The distance between...

Page 14: ...dry during installation 2 Install the group cable 3 Attach the cable to the supporting section using UV resistant cable binders 4 Install and wire the subsequent module rows Observe the polarity Obser...

Page 15: ...sed solely on the usability of the Suntub itself and only on that component no liability is accepted for loss of yield or for assembly and disassembly costs in case of damage Maintenance Cleaning Liab...

Page 16: ...Pte Ltd 72 Bendemeer Road 07 01 Luzerne Singapore 339941 Singapore SolarWorld Korea Ltd Gangnam Finance Center 16F Yeoksam dong Gangnam gu Seoul 135 925 South Korea 1 2 3 6 5 4 7 8 9 10 Production 1 D...

Reviews: