Quick Start – Solaria PowerXT-R-AC Module
© 2019 Solaria Corporation All rights reserved. Contents Subject to change.
Quick Start Guide
Solaria PowerXT-R-AC Module Mounting
Guidelines
Step 1. Plan and install the racking
Allowable rail locations with example of typical rail
configuration shown back of module view.
Step 2. Position the Enphase Q cable
A. Plan each cable segment to allow drop connectors
on the Enphase Q Cable to align with each AC
Module. Allow extra length for slack, cable turns,
and any obstructions.
B. Lay out the cabling on the racking for the AC branch
circuit. Make sure the cable is positioned in a way
that allows you to connect it to the microinverter.
Redefining Home Solar
12”
4” CLAMPING
AREA
6” CLAMPING AREA
FRAME
Step 3: Connect the Enphase Q Cable into the junction box (Transition box to your homerun wiring)
Step 4: Terminate the Unused End of the Cable
Step 5: Ground the system