Connecting to the Battery
To simplify the connection process it is advised to connect the battery to the inverter
before
mounting
the battery according to the manufacturer instructions.
Follow these guidelines:
l
For easy access to battery connectors, it is recommended to connect the cables to the battery and
to set all the battery DIP switches to their correct positions while the battery is still on the ground,
before
mounting the battery according to the manufacturer instructions). The following procedure is
recommended:
a. Connect all the wires to the battery connection panel
b. Mount the battery
c. Assemble the conduit between the battery and the inverter
d. Connect to the Connection Unit.
l
Measure the necessary length between the Connection Unit and the battery for all cables. The
maximum distance between the battery and the inverter is 35 ft/ 10 m, when using 24 AWG/ 0.2 mm
2
cables for battery control.
l
Tie and wrap the cables to avoid pulling them out during mounting.
l
Be sure to adhere to all safety cautions and information in the battery documentation.
l
The battery connects to the DC side of the inverter. Since the inverter DC connections are on its left
side, it is recommended to position the battery to the left of the inverter to simplify wiring.
WARNING!
The battery should be powered OFF before and during wiring. Turn OFF:
l
The auxiliary power supply switch
l
The circuit breaker switch
La batterie doit être étteinte avant et pendant le câblage. Fermer:
l
Le commutateur d'alimentation auxiliaire
l
Le commutateur du coupeur
SolarEdge
-
StorEdge Installation Guide MAN-01-00262-1.3
34
Connecting to the Battery