Inserting the clamps. Ensure the frame of PV module is
fully in contact with the universal clamp.
Slightly slide the next PV Module into the other side of
universal clamp, ensure the frame of PV Module is
closely in contact with the universal clamp. Visually
check to ensure the universal clamp and PV module are
properly positioned. Then tighten the universal clamp
bolt to 18-20 Nm.
Ensure both module frame edges are located on top of
the protrusions of the earthing plate.
Repeat the last two steps for each remaining module in
the row.
Place a universal clamp into the end of each rail. Ensure
that the end clamps are tight against the module and
are at least 25 mm from the rail ends.
Ensure the frame of module is located on top of the
protrusions of the earthing plate. Tighten the universal
clamp bolts to minimum of 17 Nm.
Minimum: 25 mm