3.2
ROUTINE OPERATION
No complicated procedures are required - the following simple steps will optimise performance:
POWER
1.
All load equipment switches in OFF position
UP:
2.
Power conditioner input circuit breaker to ON position.
3.
Switch ON load equipment in correct sequence - if possible do not power
up more than one item of equipment simultaneously.
POWER
1.
Power down load equipment in proper sequence.
DOWN:
2.
Switch input circuit breaker to OFF position.
NOTE - The steps above should be followed because:
1. Output voltage of the power conditioner is allowed to stabilise before being applied to load
equipment.
2. Possible problems due to overload should be avoided.
3. The power conditioner is switched off when not required. Because the resonant circuit is
energised whenever the power conditioner is energised (whether loaded or not) the
standing, or no-load losses are significant. Additionally, since MTBF refers to operational
hours (whether loaded or not), the already excellent total life expectancy will be increased.
- 9 -