- 6 -
- 7 -
1)
Placement
Install the UPS in a protected area with adequate airflow and free of excessive
dust. Do not operate the UPS outdoors.
2)
Connect to Utility
Connect the AC input connector to utility power to power up the UPS.
3)
Charge the Battery
The UPS charges its battery whenever it is connected to utility power. For best
results, charge the battery for 4 hours in the initial use.
4)
Connect the Load
Connect the loads to the output connectors on the rear of the UPS.
Installation Instructions
Operating Instructions
1)
Battery Power Outlets
The Battery Power output outlets will provide protection from surges and power
failures. Plug your computer, monitor, and other “data critical” devices into
these outlets.
2)
Surge Protected Outlet
The outlet can offer protection against surges and transients (typically caused by
lightning or disruptive loads in the building). In the event utility power failure, this
outlet will turn off. Utilize this outlet with less critical devices such as a printer,
scanner, fax, or external speakers.
3)
Switch On
With the UPS plugged in, press and hold the on/off/test/silence button more
than 1 second until “LINE NORMAL” LED lit to switch the ups on. The UPS will
perform self-testing each time when it is switched on.
4)
Switch Off
By pressing and hold the on/off/test button more than 2 seconds until the
“LINE NORMAL” or “BACK UP” LED off to switch the UPS off.
5)
Self-test
Use the self-test to verify both the operation of the UPS and the condition of the
battery. In normal utility power, push the on/off/test button less than 1 second
and UPS performs a self-test function. During the self-test, the UPS runs in back
up mode. If the UPS passes the self-test, it returns to
“LINE NORMAL” operation.
Rear Panel (1500 VA)
2) Remote Port (option)
3) Phone Jack (option)
4) UPS Output Outlets
5) AC Input Receptacle
6) AC Fuse Breaker
3
4
6
2
4
5
Troubleshooting
PROBLEM
PROBABLE CAUSE
ACTIOn TO TAKE
UPS not on,
LED will not light
UPS is off or On/Off/Test button not pushed
long enough.
Press the Power On/Off/Test button
more than 2 seconds.
Battery voltage less than 10V (20V for S1K1500)
Recharge the UPS at least 4 hours.
If unit still does not start, check the
input fuse.
Other failure
Call Technical Services
Load less than 20W in back-up mode
Normal condition
UPS always in
back-up mode
Power cord loose
Re-plug the power cord
AC Fuse opened
Replace the AC Fuse
Line voltage too high, too low, or black out
Normal condition
Other failure, PCB, etc.
Call Technical Services
Back-up time
too short
Battery not fully charged
Recharge the UPS for
at least 4 hours
Other failure
Call Technical Service
Continuous Beep
Overload condition
Remove the non-critical loads
Red LED
Illuminated
Battery failure
Call Technical Services
Summary of Contents for S1K320
Page 2: ......