background image

 

 

INPUTTING MOTOR DATA SAMPLE 

1)

 

If the data in the drive doesn’t match the existing equipment, use 
the following procedures to correct the values: 

a)

 

Press 

UP

  arrow  key  to  access  the  motor  output  power 

parameter T2-04. 

b)

 

Press 

ENTER

 key to view the default setting. 

c)

 

Press 

F1

 (left), 

F2

 (right), 

RESET

UP

 and 

DOWN

 arrow keys to 

enter the motor power nameplate data in kW – (kW) = (Motor 
HP) x (.74)  

i)

 

Example:   12 HP   x   .74   =   8.88 kW

 

(in this example T2-

04 would be 8.88)

 

d)

 

Press 

ENTER

 key to save the setting 

e)

 

The display automatically returns to the display in Step 2. 

2)

 

After verifying the data listed on the motor nameplate, press 

UP 

arrow key to confirm and get to “Tuning Ready” message. 

3)

 

Press and hold down the M Contactor during the duration of the 
Auto-Tune. 

4)

 

Press 

RUN 

to activate Auto-Tuning.  

Auto-Tuning finishes in approximately one to two minutes 

Encoder Auto-Tuning 

1

st

 Phase Encoder Auto-Tuning 

1)

 

Press 

ENTER

 key to select the value for T2-01. 

2)

 

Set T2-01 to “

3

” and save the setting by pressing 

ENTER

3)

 

Press and hold down the M Contactor. 

4)

 

Press 

RUN 

to activate Auto-Tuning. 

2

nd

 Phase Encoder Auto-Tuning 

1)

 

Press 

ENTER

 key to select the value for T2-01. 

2)

 

Set T2-01 to “

4

” and save the setting by pressing 

ENTER

3)

 

Press and hold down the M Contactor. 

4)

 

Press 

RUN 

to activate Auto-Tuning.

 

** Remove the temporary jumper from drive H1 to REF. ** 

The Two-Phase Encoder Auto-Tunings finish very fast 

Summary of Contents for Magnetek L1000A

Page 1: ...DRIVE STARTUP MANUAL Magnetek L1000A Drive Permanent Magnet Installation www smartrise us 2601 Fair Oaks Blvd Sacramento CA 95864 916 457 5129...

Page 2: ...le on the drawings Sheet 1 Getting Started matches the actual equipment Below is a sample table showing the important values that will affect operation Sample Sheet 1 Getting Started Motor Volts Motor...

Page 3: ...side of the incoming water main To a grounding rod that has been driven into the pit flooring The controller has a common ground bus terminal connection All grounds need to land at this common point i...

Page 4: ...ls K1 K2 and the secondary brake wiring if equipped to terminals J1 J2 located on the terminal block next to the M contactor Jump EB to the terminal listed in the Construction box located on Sheet 01...

Page 5: ...s if required Pre Transfer Emergency Power Governor IMPORTANT REMOVE FACTORY WIRES ON INPUTS 521 522 o Install the Run Bug Up Down Switch to IO s 521 522 Install the Run Bug Up Down Enable switch to M...

Page 6: ...ck off box when complete Toggle the Inspection Normal switch to the INSP position Set BYPASS TERM LIMITS to YES o On the Smartrise Machine Room controller board press the Left Arrow ESC button several...

Page 7: ...press the enter key o Use the Up Down Arrow keys to change the word NO to YES o Use the RIGHT Arrow key and move the asterix under the word SAVE and press enter o Hit the LEFT Arrow ESC button several...

Page 8: ...ntil the Auto Tuning display appears 4 Press ENTER key to begin setting parameters a Press ENTER key to select the value for T2 01 Set to 1 5 Save the setting by pressing ENTER 6 The display automatic...

Page 9: ...motor nameplate press UP arrow key to confirm and get to Tuning Ready message 3 Press and hold down the M Contactor during the duration of the Auto Tune 4 Press RUN to activate Auto Tuning Auto Tuning...

Page 10: ...ection Make sure the car is moving in the same direction as the control switch on the Run Bug o Go to Troubleshooting Wrong Direction for corrective actions At Speed Make sure that the car is moving a...