STP60-JP-10-IA-en-11
Installation Manual
4 Service
4.1 Troubleshooting and Repair
The information is organized in tables showing messages
appearing in the LCS tool, known as events. The tables
contain descriptions of events as well as explanations of
which actions to take when an event occurs.
Grid-Related Events
Type of event
Indicates whether the event is of the grid, PV, internal or fail safe category.
ID
The specific event ID.
Display
Text shown in display.
Description
Description of the event.
Measure
Description of which action to take prior to contacting any other parties.
DNO
If the prescribed action has not identified the malfunction, contact the DNO for further assistance.
SMA Service Line
If the prescribed action has not identified the malfunction, contact Service for further assistance
(see Section 6 “Contact”, page 37).
PV
If the prescribed action has not identified the malfunction, contact the PV module supplier for
further assistance.
ID
Status
message
Description
Measure
DNO SMA
Service
Line
PV
1–6
Grid voltage too low.
Check voltage and AC installation.
If the voltage is zero, check the
fuses.
x
-
-
7–9
Grid voltage average too high
for ten minutes.
Check that the installation is correct
in accordance with the installation
manual. If so, request a new grid
code file with increased voltage
limit or reactive power for voltage
suppression.
x
-
-
10–15
Grid voltage too high.
Check voltage and AC installation.
x
-
-
16–18
The inverter has detected a
voltage peak on the grid.
Check voltage and AC installation.
x
-
-
19, 22
Grid frequency too low or too
high.
Check power frequency.
x
-
-
28–30
Grid frequency change
exceeded.
Check deviation of the grid
frequency.
x
-
-
31–33
DC current share in utility grid
is too high.
For repeated daily occurrences,
perform onsite grid analysis.
-
x
-