7 Commissioning
7.1 Procedure
Procedure
See
1.
Check which country data set the inverter is set to.
Supplementary sheet
with the default settings
or type label
2.
If the country data set is not set correctly for your country or
your purpose, adjust to the required country data set and the
corresponding display language within the first ten feed-in
hours via the rotary switches in the inverter.
Section 7.2, page 28
3.
Commission the inverter.
Section 7.3, page 30
7.2 Configuring the Country Data Set
Set the country data set appropriate for your country or purpose within the first ten feed-in hours via
the rotary switches in the inverter. After the first ten feed-in hours, the country data set can only be
changed by means of a communication product.
Country data set for operation with external decoupling protection
When operating the PV system with external decoupling protection, the inverter has the
additional country data set
Medium-Voltage Directive (Germany)
. This country data set
allows you to extend the operating range of the inverter for voltage and frequency. This
country data set should only be selected if the PV system is disconnected via external
decoupling.
• If you set the country data set for operation with external decoupling protection, you must
only operate the inverter with an external three-phase decoupling protection. Without
external three‑phase decoupling protection, the inverter will not disconnect from the utility
grid when the country-specific standard requirement is exceeded.
Rotary Switch Positions
Rotary switch A
Rotary switch B
Country data set
0
0
Default setting
1
0
VDE0126-1-1
1
2
VDE-AR-N4105*
1
6
VDE-AR-N4105-HP**
1
B
VFR2014
2
8
AS4777.3
1
3
2
CEI 0-21 external
1
***
7 Commissioning
SMA Solar Technology AG
Operating Manual
STP20-25TL-BE-en-10
28