5 Mounting
SMA Solar Technology AG
Operating manual
SBS25-1VL-10-BE-en-13
26
Dimensions for mounting:
105
105
240
334
23
357
450
Figure 7: Position of the anchoring points(Dimensions in mm)
Recommended clearances:
If you maintain the recommended clearances, adequate heat dissipation will be ensured. Thus, you
will prevent power reduction due to excessive temperature.
☐ Maintain the recommended clearances to walls as well as to other inverters or objects.
☐ If multiple inverters are mounted in areas with high ambient temperatures, increase the
clearances between the inverters and ensure sufficient fresh-air supply.