7 Commissioning
SMA Solar Technology AG
Installation Manual
SBxx-1SP-US-40-IA-xx-15
51
7
Commissioning
7.1
Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure
See
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
• Direct connection via WLAN
• Direct connection via Ethernet
• Connection via WLAN in the local network
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Select the inverter configuration option. Please note that
the SMA Grid Guard code for changing the grid-relevant
parameters must be available after completion of the first
ten feed-in hours or installation assistant (see "Application
for the SMA Grid Guard code" available at www.SMA-
Solar.com).
5.
Ensure that the country data set has been configured cor-
rectly.
Inverter user manual
6.
Make further inverter settings as needed.
Inverter user manual
7.2
Commissioning the Inverter
Requirements:
☐ The AC circuit breaker must be correctly rated and mounted.
☐ A means of disconnecting the inverter from the PV array must be present.
☐ The inverter must be correctly mounted.
☐ All conductors must be correctly connected.
☐ Unused enclosure openings must be sealed tightly with sealing plugs.