CARRIER STUD PLACEMENT
I if using
in-wall carrier, set bearing rods as
shown above.
SET DRAIN LINE HEIGHT
17” from
finished floor (standard 24” rim) or 10” for
ADA installation. Threaded nipple should
extend ½ to ¾” from wall.
A. Clean face
of existing drain nipple.
B. Install the clear inspection disc
with
compression nut.
C. Slowly pour water
into the drain.
D. Use a flashlight to check the pitch/
slope
. No water should be present in
the inspection disc or nipple.
E. Remove disc
and nut after inspection.
"
DRILL HOLES
masonry
bit for the lower anchor screws
and mounting plate and insert
plastic anchors where indicated.
TIGHTEN COMPRESSION
NUT AND HOSE CLAMP.
DETERMINE THE DRAIN NIPPLE DEPTH
by measuring the distance between the
back of the sanitary tee (or elbow) to
the front edge of the nipple.
MEASURE & MARK THE ROUGH-IN
if
"
masonry bit to drill hole, then install
the hanger bracket with one plastic
anchor and screw.
"
ADJUST DRAIN TO ACHIEVE PITCH
only if standing water is present
(code requires ¼” drop per foot of
drain line for proper pitch). Seal wall
according to code.
A.
Hang the bowl on the bracket
and check tail
pipe alignment, then remove the bowl and
adjust the bracket as needed.
Re-hang and re-check bowl
alignment with
the drain line. Tail pipe should align with center
of drain line.
B.
Mark anchor holes
then
remove bowl without
moving hanger bracket.
INCORRECT
Not centered
CORRECT
Centered
A
B
½"
to
¾"
10"
for ADA
installation
standard 24" rim
finished floor
17"
2¼
1 ⁄
1 "
13 ⁄ "
Drain
Cut away wall
Lift drain line & brace
with mending plate
Install two
additional screws
A.
Find the drain nipple depth
on
the Tube Cutting Chart (left).
Measure and mark the specified
trim length
on the insert tube at
the nearest ¼” groove.
B.
Cut the tube
at the groove using a sharp
utility knife to ensure a square, flat cut.
C.
Clean burrs
from the cut end by using
emery paper.
D.
Apply lubricant
to the outside of the
rubber bushing and ribbed inside area.
E.
Insert the tube
and bushing with arrow
tab at the top. Apply lubricant to tailpipe
of housing.
IMPORTANT:
Be sure arrow tab
is at 12:00 position.
1
2
3
4
Arrow
tab UP
1
2
3
4
A
C
B
D
E
POUR 5
GALLONS
OF WATER
as rapidly
as possible
into housing
to ensure
good flow
and no leaks or
standing water.
CAULK THE BOWL
TO THE WALL
if
there is good flow
and no leaks or
standing water.
INSTALL
CARTRIDGE
per the cartridge
instruction sheet.
CARTRIDGE
INSTRUCTIONS
HANG THE BOWL,
inserting tailpipe
into bushing, then install anchor
screws with washers.
PLACE THE HOSE CLAMP
and compression nut onto the
housing tailpipe.
13 ⁄ "
Install plastic anchor
and screw here
14
15
4
13
3
12
8
6
2
10
11
7
5
1
C
D
9
WES-7000 WATERFREE URINAL
NEW CONSTRUCTION
INSTALLATION INSTRUCTIONS
BEFORE STARTING INSTALLATION:
IMPORTANT
Do not install on copper DWV
due to copper’s susceptibility to corrosion.
Check rough-in height to achieve 24” rim height
(17” rim height for ADA).
Check slope. Downhill slope, per code, is essential
because waterfree urinals depend on gravity flow.
Check DWV material. Suitable materials include
cast iron, PVC, ABS and galvanized steel.
TUBE CUTTING CHART
Measure drain nipple depth (inches) to find trim
length (inches)
13 7/8” or more DO NOT CUT
3 3/4” or less DO NOT USE TUBE
•
•
•
•
•
•
OR LESS
TRIM
13 ¾"
¼"
13 ½
½
13 ¼
¾
13
1
12 ¾
1¼
12 ½
1½
12 ¼
1¾
12
2
11 ¾
2¼
11 ½
2½
11 ¼
2¾
11
3
10 ¾
3 ¼
10 ½
3 ½
OR LESS
TRIM
10 ¼"
3 ¾"
10
4
9 ¾
4 ¼
9 ½
4 ½
9 ¼
4 ¾
9
5
8 ¾
5 ¼
8 ½
5 ½
8 ¼
5 ¾
8
6
7 ¾
6 ¼
7 ½
6 ½
7 ¼
6 ¾
7
7
OR LESS
TRIM
6 ¾"
7 ¼"
6 ½
7 ½
6 ¼
7 ¾
6
8
5 ¾
8 ¼
5 ½
8 ½
5 ¼
8 ¾
5
9
4 ¾
9 ¼
4 ½
9 ½
4 ¼
9 ¾
4
10
CUSTOMER SERVICE
1-888-SLOAN-14 (1-888-756-2814)
www.sloanvalve.com
The information in this document is subject to change without notice.
© 2015 Sloan Valve Company All rights reserved.
(08-15)Rev1
CAUTION
After removing any urinal from the
drain line, it’s normal for certain naturally occurring,
but potentially hazardous sewer gases to escape
through the opening until the waterless cartridge
is installed properly into the waterless urinal. If you
need to leave an open drain line unattended after
removing the urinal from the wall, temporarily wedge paper towels or a
rag into the drain hole to reduce any outflow of sewer gases, and remove
the paper towels or rag prior to completing the urinal or cartridge
installation.
Never smoke, have an open flame, or place your nose or
mouth near open drain lines or waterless urinal housings into which
a cartridge is not yet properly installed.
You also can wear a breathing
mask when removing or installing any waterless urinal or cartridge to
reduce potential exposure to any such gases.
•
LUBRICANT
in-wall carrier is not used. Use a
11
10
12