INSPECTION

Your boiler and heating system will last an indefinitely
long time at full efficiency, if it is inspected regularly
and is kept in good repair and adjustment. You, the
user, should make regular inspections, and report  any
problems to your service agency. At regular intervals,
you should have that agency inspect the system, clean
the boiler and make repair adjustments as necessary.
What you and the service agency should do is listed
below. Contact your gas supplier for a list of qualified
service and repair agencies.

USER INSPECTION

The user should make the following inspections at
least once each month during the heating season and
once just before cold weather starts:

1. Venting system inspection

A.

Horizontal or vertical venting inspection
All Victory 

II

boilers may be vented horizontally

through an outside wall (see Figure 2), through
the roof (see Figure 3) or vertically utilizing an
existing chimney as a chase (see Figure 4). In
all cases a 3" diameter AL29-4C* stainless steel
venting material MUST be used.

Inspect the system regularly for condensation,
corrosion and/or physical damage. A qualified
professional should service the boiler annually
and include such an inspection at that time. The
homeowner should look over the system month-
ly for damage, water stains, any signs of rust,
other corrosion or separation of the flue (vent)
and fittings.

Should an inspection turn up signs of condensa-
tion, corrosion or damage, the boiler should be
shut down immediately and the condition should
be corrected by a qualified professional.

If the boiler is vented horizontally through the
wall, the outside termination and screen should
be checked for any debris blocking the opening
and cleaned as required.

B.

Chimney or Type “B” venting inspection
Only models VHS-90, VHS-120, VHS-150 and
VHS-180 may be vented directly into a chimney
with 5, 6, or 7 inch diameter standard metal smoke
pipe (galvanized). See Figure 5. Make sure pipe
joints are snug and are fastened with screws. The
chimney joint should be filled with cement to pre-
vent leakage. There should be no visible signs of
rust or salts from water evaporation.

*: AL29-4C is a registered trademark of Allegheny Ludlum Corp.

Figure 2. Horizontal venting, side wall venting

Figure 3. Vertical venting through the roof

3

Summary of Contents for VHS-120

Page 1: ...diately call your gas supplier from a neighbor s phone Follow the gas supplier s instructions If you cannot reach your gas supplier call the fire department Installation and service must be per formed...

Page 2: ...your family with many years of reliable comfort and trouble free performance The care and maintenance of your new boiler is important to prevent a hazardous condition which might result from lack of...

Page 3: ...Inspect the system regularly for condensation corrosion and or physical damage A qualified professional should service the boiler annually and include such an inspection at that time The homeowner sho...

Page 4: ...eve the pressure Call your service organization if pressures are higher or lower than normal and if the relief valve spills water Repair or adjustment is needed 5 Unusual noise Stand near the boiler a...

Page 5: ...4 for instruction 4 Piping inspection Check the following A Water piping and accessories for leaks Slightest leaks should be corrected B System to be full of water and pressure to remain stable at co...

Page 6: ...ry II boilers are equipped with a single use flame roll out safety shut off switch It will shut off main gas burners in the event the flow of combustion prod ucts through the boiler flue passages are...

Page 7: ...er for propane to clear out any gas Then smell for gas including near the floor If you smell gas STOP Follow B in the safety information on page 6 If you don t smell gas go to next step 7 Turn gas con...

Page 8: ...SLANT FIN CORPORATION Greenvale N Y 11548 Phone 516 484 2600 FAX 516 484 5921 Canada Slant Fin LTD LTEE Mississauga Ontario www slantfin com...

Reviews: