1.

 

Assemble beam using 2 splice plates and 8 bolts and nuts per joint.  Rolling Roof Rig Package 154-24-A 

consists of 2 end beams.  Package 154-24-B consists of 2 end beams and 1 mid-beam.  

 

2.

 

Raise the mast to the desired height and insert the retaining pin.  Loosen the 4 nuts and bolts connecting the 

hat bracket to the mast.  Insert and pin a jack on each side of the stanchion.  Repeat with second mast.  

 

3.

 

Insert the assembled I-beam through the hat bracket of the front stanchion until you reach the desired amount 

of outreach.  Tighten the four hat bracket nuts and bolts.  Insert other end of I-beam through rear stanchion 

until about 3 inches of the beam extends beyond the hat bracket (packages 154-24-A and 154-24-B).  

 

4.

 

Remove the two bolts on either side of the rear hat bracket.  Set the Longhorn on top of the rear hat bracket 

and secure it using the two bolts.  

 

5.

 

Check chart to determine maximum amount of outreach for your application.  If a strongback is required see 

package 154-24-C or 154-24-CBT.  

 

6.

 

Roll the assembled roof rig into the desired location.  Crank the jacks until the load is removed from the casters 

and the roof rig is level.  

 

7.

 

Slide the correct number of counterweights (see chart on page 6) onto the longhorn rods.  Slide the large 

washers onto the rods and place a bale clip or nut and bolt through the ends of the rods to retain the 

counterweights.  

 

8.

 

Attach the tie back wire rope to the hole in the rear of the I-beam or the shackle of the suspension rope and 

tie back to a substantial building structure*.  

*Substantial building structures are defined and verified as an anchor point designed and confirmed in writing by an engineer, 
with a 4:1 safety factor versus the rating of the hoist being used.    

 

9.

 

Attach the suspension wire rope assembly counterweights to the hole in the front of the I-beam.   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

16-foot Rolling Roof Rig 

(plus counterweights) 

8-foot End 

Beam 

Double 

LongHorn 

Beam Tube  

(or splice plates) 

Rolling Roof  

Rig Stands 

Rolling 

Roof Rig 

Stands 

Splice Plate  

alternative to beam tubes 

Summary of Contents for Rolling Roof Rig

Page 1: ...ng Roof Rig Assembly Instructions Rolling Roof Rig Corner Adaptor and Beam Splice Tube Packages Sky Climber LLC 1800 Pittsburgh Dr Delaware OH 43015 Tel 1 800 255 4629 info skyclimber com www skyclimber com ...

Page 2: ...ounterweights are non flowable type secure and in the correct quantities Cornice hooks parapet clamps or outriggers are secured and tied back Tiebacks are tight and straight back or two opposing tie backs are used contact Sky Climber Engineering for details Wire rope inspected and is not kinked bird caged or otherwise damaged or overly worn Minimum of three 3 J Clamps fist grips are used and are p...

Page 3: ... hat bracket and secure it using the two bolts 5 Check chart to determine maximum amount of outreach for your application If a strongback is required see package 154 24 C or 154 24 CBT 6 Roll the assembled roof rig into the desired location Crank the jacks until the load is removed from the casters and the roof rig is level 7 Slide the correct number of counterweights see chart on page 6 onto the ...

Page 4: ...he outermost holes of the beam allowing for assembly without tools Look through the inspection slot to verify that beam is fully inserted into the beam tube If you can see through to the inspection slot on the opposite side of the beam tube then the beam is not fully inserted Some beams also feature a label that will be partially visible once inserted into the beam tube If the green portion of the...

Page 5: ...mplete a final adjustment using the screw jack wing nut Note that the load should be spread on the roof floor with the use of appropriate cribbing Tighten the wing nut to secure the screw jack height Insert the mast of the front RRR stand in to the long tube of the Corner Adapter and adjust the height as required Assure the rear Rolling Roof Rig stand is set to the correct height to ensure a level...

Page 6: ...29 info skyclimber com www skyclimber com 6 Print Date 11 18 2019 SCL_AssemblyInstructions_RRR_RevAA_2019 11 18 Counterweights 24 foot Rolling Roof Rig WITH Strongback 24 foot Rolling Roof Rig 16 foot Rolling Roof Rig ...

Reviews: