© Jul.2020
5-6
GTJZ0612E&0812E&1012E&1212E Maintenance Manual
1.
Open the right door of the chassis and locate the
hydraulic valve block.
2.
Disconnect and plug the hoses and fittings on the
valve block, and tag the machine.
3.
Remove the screws installed at the bottom of the
valve block.
4.
Remove the valve block.
Installing the Cartridge Valve
NOTICE
When installing the removed hose and fitting, it must
be tightened according to the specified torque. See
Hydraulic Hose and Fitting Specifications, page
1-9
.
1.
Immerse the valve into clean oil and lubricate the O-
ring.
2.
Screw in the cartridge valve by hand until the O-ring
contacts the valve block. Tighten as per the speci-
fied torque.
3.
Install the solenoid coil of the valve on the valve
rod. Properly install the coil nut and tighten as per
the specified torque if necessary.
Figure 5-7
Table 5-1
No
Description
Function
Tightening Torque
1
Pressure port
Measuring pressure
40 Nm (30 ft-lb)
2
2-position 4-way solenoid valve
Platform lifting
34 Nm (25 ft-lb)
3
3-position 4-way solenoid valve
Left/right steering
34 Nm (25 ft-lb)
4
Lifting overflow valve
Lifting overflow
27 Nm (20 ft-lb)
5
Steering overflow valve
Steering overflow
24 Nm (18 ft-lb)
旧底图总号
日 期
签 字
校 描
描 图
借通用件登记
2
A
B
1
2
3
4
5
Summary of Contents for GTJZ0612E
Page 2: ......
Page 6: ...This Page Intentionally Left Blank...
Page 8: ...This Page Intentionally Left Blank...
Page 12: ...Jul 2020 iv GTJZ0612E 0812E 1012E 1212E Maintenance Manual This Page Intentionally Left Blank...
Page 86: ...Jul 2020 5 28 GTJZ0612E 0812E 1012E 1212E Maintenance Manual MAINTENANCE PROCEDURES...