Doc
.
No:
Version:
2
PROCEDURES
WARNING
HIGH VOLTAGES ARE PRESENT
.
TURN OFF POWER
BEFORE INSTALLATION OR SERVICING.
The use of temporary ground during installation and maintenance is recommended
.
1)
Install one washer over the threads at the end of the SP-36 housing. Push the washer
up against the housing.
2)
Choose a knockout in the load center that is a distance from the backboard that will
allow the back of the SP-36 to lay flat against the backboard.
3)
Install the second washer on the threads at the end of the SP-36 housing from inside
the load center
.
Install the lock nut so that it loosely holds the SP
-
36 in place.
4)
Use the wood screw provided to secure the SP-36 mounting tab to the backboard
.
5)
Tighten the lock nut installed in step 3 for a snug fit.
Cut the wires on the SP-36 to the minimum usable length
.
Do not coil the wires as this
greatly reduces SP-36 performance
.
Also
,
avoid kinks and sharp bends in the wiring
.
7) Connect the wires to the load center, observing the proper hook-up scheme.
8) The wires must be connected so that there is a fuse or circuit breaker between the SP-
36 and the power service line.
HOOK UP SCHEMES