Advanced commissioning
7.9 Safe Torque Off (STO) safety function
Converter with control units CU250D-2
270
Operating Instructions, 04/2015, FW V4.7.3, A5E34261542B AB
Reduced acceptance after functions have been expanded
A full acceptance test is necessary only after first commissioning. A reduced acceptance test
is sufficient when safety functions are expanded.
Measure
Acceptance test
Acceptance test
Documentation
Functional expansion of the ma-
chine (additional drive).
Yes.
Only check the safety
functions of the new
drive.
•
Supplement machine overview
•
Supplement inverter data
•
Add function table
•
Log the new checksums
•
Countersignature
Transfer of inverter settings to
other identical machines by means
of series commissioning.
No.
Only check the control
of all of the safety
functions.
•
Add machine description
•
Check checksums
•
Check firmware versions
Documents for acceptance
The STARTER provides you with a number of documents to be regarded as a
recommendation for the acceptance tests of the safety functions.
Procedure
Proceed as follows to create the acceptance documentation for the drive using STARTER:
1.
In STARTER, select "Create acceptance documentation":
STARTER has templates in German and English.